Lien deadlines · Alaska

Alaska mechanics lien deadlines: notice, lien and suit (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

If a notice of completion is not recorded by the owner as provided in AS 34.35.071, Alaska's lien filing deadline is 120 days after the claimant completes the construction contract or ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's property (AS 34.35.068(a)). The deadline to sue is 6 months after the claim of lien is recorded (AS 34.35.080(a)).

Alaska · Lien deadlinesVerified 2026-10-02
Lien filing
If a notice of completion is not recorded by the owner as provided in AS 34.35.071: 120 days after the claimant completes the construction contract or ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's property; If a notice of completion is recorded by the owner, for a claimant who has received advance notification of the date it is recorded or who has not given a notice of right to lien, to record a claim of lien or a notice of right to lien: 15 days after a notice of completion is recorded; If a notice of completion is recorded by the owner, for a claimant who records a notice of right to lien before or within that 15-day period, or who has given a notice of right to lien but has not received advance notice of the date the notice of completion is recorded: 120 days after the claimant completes the construction contract or ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's property
Preliminary notice
None required
Deadline to sue
6 months after the claim of lien is recorded

Preliminary notice

WhoProject typeBranchDeadlineStatute
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyDefaultNone requiredStatute: AS 34.35.064(a)
Before furnishing labor, material, service, or equipment for a project, a person may give a notice of right to lien to the owner or owner's agent.
AS 34.35.064(a) · Official text · retrieved 2026-09-30

Lien filing

WhoProject typeBranchDeadlineStatute
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyIf a notice of completion is not recorded by the owner as provided in AS 34.35.071120 days after the claimant completes the construction contract or ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's propertyStatute: AS 34.35.068(a); AS 34.35.068(c)
What the statute says about it. A claim of lien is enforceable only if recorded within the time AS 34.35.068 specifies.
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyIf a notice of completion is recorded by the owner, for a claimant who has received advance notification of the date it is recorded or who has not given a notice of right to lien, to record a claim of lien or a notice of right to lien15 days after a notice of completion is recordedStatute: AS 34.35.068(b); AS 34.35.068(c)
What the statute says about it. A claim of lien is enforceable only if recorded within the time AS 34.35.068 specifies.
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyIf a notice of completion is recorded by the owner, for a claimant who records a notice of right to lien before or within that 15-day period, or who has given a notice of right to lien but has not received advance notice of the date the notice of completion is recorded120 days after the claimant completes the construction contract or ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's propertyStatute: AS 34.35.068(b); AS 34.35.068(a); AS 34.35.068(c)
What the statute says about it. A claim of lien is enforceable only if recorded within the time AS 34.35.068 specifies.
(a) If a notice of completion is not recorded by the owner as provided in AS 34.35.071, a claim of lien shall be recorded not later than 120 days after the claimant (1) completes the construction contract; or (2) ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's property.
AS 34.35.068(a) · Official text · retrieved 2026-10-02
A claim of lien is enforceable only if recorded by a claimant within the time specified in (a) or (b) of this section.
AS 34.35.068(c) · Official text · retrieved 2026-09-30
(b) If a notice of completion is recorded by the owner as provided in AS 34.35.071, (1) the following shall record a claim of lien or a notice of right to lien not later than 15 days after the notice of completion is recorded: (A) a claimant who has received advance notification of the date that the notice of completion is recorded as provided in AS 34.35.071(a)(2); (B) a claimant who has not given a notice of right to lien as permitted in AS 34.35.064; (2) the following shall record a claim of lien not later than the time specified in (a) of this section: (A) a claimant who records a notice of right to lien before or within the period specified in (1) of this subsection; (B) a claimant who has given a notice of right to lien but who has not received advance notice of the date that the notice of completion is recorded by the owner as provided in AS 34.35.071(a)(2).
AS 34.35.068(b) · Official text · retrieved 2026-10-02

Deadline to sue

WhoProject typeBranchDeadlineStatute
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyDefault6 months after the claim of lien is recordedStatute: AS 34.35.080(a)
What the statute says about it. The lien does not bind real property for more than six months after the claim of lien is recorded unless an action to enforce it is commenced in the proper court within that time, or within six months after an extension notice recorded in the same recording office within the original six-month period.
(a) A lien provided for in AS 34.35.050 — 34.35.120 does not bind real property for more than six months after the claim of lien is recorded, unless an action is commenced in the proper court to enforce the lien within (1) that time; or (2) six months after recording of an extension notice in the same recording office within the original six-month period showing the recording date and the book and page or instrument number or serial number of the initial claim of lien, and the balance owing.
AS 34.35.080(a) · Official text · retrieved 2026-10-02

Notice of commencement and completion

The owner may announce the date of completion by recording a notice of completion after completion of the project, and by giving notice at least five days before recording it to every claimant who gave the owner and the lender a notice of right to lien or a stop-lending notice earlier than 10 days before the recording. A notice of completion recorded before completion is not effective.

(a) The owner of real property that may be subject to a lien under AS 34.35.050 — 34.35.120 may announce the date of completion of the project by (1) recording a notice of completion after completion of the project in the office of the recorder of the district in which the real property is situated; and (2) giving notice at least five days before the recording of the notice of completion to all claimants who have given a notice of right to lien or a stop-lending notice to the owner and the lender prior to 10 days before recording a notice of completion; the notice must include a copy of the notice of completion and a statement advising claimants that a notice of completion will be recorded not earlier than five days after the date of the notice.
AS 34.35.071(a) · Official text · retrieved 2026-10-02
(d) A notice of completion is not effective if recorded before completion.
AS 34.35.071(d) · Official text · retrieved 2026-10-02

How the days are counted

The day of the event is not counted, and the last day of the period is.

The time in which an act provided by law is required to be done is computed by excluding the first day and including the last, unless the last day is a holiday, and then it is also excluded.
AS 01.10.080 · Official text · retrieved 2026-09-30

A last day that falls on a Sunday or a legal holiday moves to the next day that is not one.

(13) every Sunday;
AS 44.12.010(a)(13) · Official text · retrieved 2026-09-30

Who the deadlines apply to

Alaska's mechanics lien periods sit in AS 34.35.050 to 34.35.140 [1]. Every rule on this page names the same five roles: direct contractors, subcontractors, sub-subcontractors, suppliers and laborers. None is limited to residential work or to work other than residential; each is written for any project type [1].

The preliminary notice stage reads None required for all five roles [1]. Its statute block is AS 34.35.064(a), the section on the notice of right to lien. The same notice appears again at the lien filing stage, where two of the three conditions also turn on whether a claimant has given or recorded a notice of right to lien [1].

How the periods run

Claim of lien. Each of the three Alaska filing rules starts with a condition about the owner's notice of completion.

If a notice of completion is not recorded by the owner as provided in AS 34.35.071, the claim of lien period is 120 days after the claimant completes the construction contract or ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's property [1].

If a notice of completion is recorded by the owner, for a claimant who has received advance notification of the date it is recorded or who has not given a notice of right to lien, to record a claim of lien or a notice of right to lien, the period is 15 days after a notice of completion is recorded [1]. This period runs from the recording of the notice of completion.

If a notice of completion is recorded by the owner, for a claimant who records a notice of right to lien before or within that 15-day period [1], or who has given a notice of right to lien but has not received advance notice of the date the notice of completion is recorded, the period is 120 days after the claimant completes the construction contract or ceases to furnish labor, material, services, or equipment for the construction, alteration, or repair of the owner's property [1].

For all three, AS 34.35.068 states the result of a late filing: a claim of lien is enforceable only if recorded within the time that section specifies [1].

Suit to enforce. The last period starts when the claim of lien is recorded: 6 months after the claim of lien is recorded [1]. Under AS 34.35.080(a), the lien does not bind real property for more than six months after the claim of lien is recorded unless an action to enforce it is commenced in the proper court within that time, or within six months after an extension notice recorded in the same recording office within the original six-month period [1].

The owner's notice of completion

Under AS 34.35.071, the owner may announce the date of completion. The owner does so by recording a notice of completion after completion of the project, and by giving notice at least five days before recording it [1]. That advance notice goes to every claimant who gave the owner and the lender a notice of right to lien or a stop-lending notice earlier than 10 days before the recording [1]. A notice of completion recorded before completion is not effective [1].

Counting the days

AS 01.10.080 counts a period set by law by leaving out the first day and counting the last [2]. When the last day is a holiday, that day is left out as well, and this applies at every stage [2]. AS 44.12.010 makes every Sunday a legal holiday, so a last day falling on a Sunday moves too [3].

The same section lists the named legal holidays and adds every day the President of the United States or the governor designates by public proclamation [3]. Under AS 44.12.020, when a listed holiday other than Sunday itself falls on a Sunday, that Sunday and the following Monday are both legal holidays [3].

Related

Lien deadlines: other states

Sources

  1. AS 34.35.050 to 34.35.140, Alaska Legislature (retrieved 2026-09-30)
  2. AS 01.10.080, Alaska Legislature (retrieved 2026-09-30)
  3. AS 44.12.010 to 44.12.025, Alaska Legislature (retrieved 2026-09-30)

Changelog

  1. : Page published.
  2. : 10 more jurisdictions published: Alabama, Alaska, Arkansas, Colorado, Connecticut, Delaware, District of Columbia, Hawaii, Idaho and Indiana.
  3. : Dataset first published: 9 of 51 jurisdictions published.