We would rather be corrected than be quoted wrongly. If a figure, citation or calculator result on this site is wrong, tell us and we will fix it.
How to report an error
Email [email protected] with the subject line Correction: <page URL>. Include the figure or sentence you are questioning, what you believe is correct, and a source if you have one. You can report an error from any page on the site.
What we do with it
We check the report against the primary source: the statute, the agency page, the IRS/DOL/SSA publication, or the vendor's pricing page. If we were wrong, we correct the page and add a dated line to the log below. If we were right, we reply and tell you why, and if the page was merely unclear we rewrite it.
We fix substantive errors as soon as we have confirmed them. Typos and formatting fixes are made silently and are not logged. Corrections that change a number, a rule, a citation or a conclusion are always logged. We do not edit them away quietly.
Corrections log
Format, one line per correction: date · page · what changed · why
This log opens on September 26, 2026 and every entry stays in it permanently.
| Date | Page | What changed | Why |
|---|---|---|---|
| /states/california/retainage/ | California's private-work row now states the 5% retention cap in Civil Code § 8811 for contracts entered into on or after January 1, 2026, with its two exceptions; it had said private retention had no statutory cap. The same row is corrected in the retainage laws by state table and its CSV and JSON downloads. | SB 61 (Stats. 2025, ch. 49) added § 8811, effective January 1, 2026. Our research predated the check against it; we read the statute on California Legislative Information on 2026-10-17. | |
| /states/missouri/retainage/ | Missouri's private-work row now states the 10% cap and the release within 30 days of substantial completion in Mo. Rev. Stat. §§ 436.300 to 436.336; it had said Missouri set no private retainage rule. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. | |
| /states/tennessee/retainage/ | Tennessee's rows now state the 5% cap on owner-to-prime retainage in Tenn. Code Ann. § 66-34-203 for public and private work, the $500,000 escrow threshold, and that public owners do not owe the $300-a-day damages; they had shown no cap above the prime and applied the damages to public owners. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. | |
| /states/idaho/retainage/ | Idaho's private-work row now states the 5% cap and the 35-day release in Idaho Code § 29-115; the page had covered public work only and left private work out. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. | |
| /states/rhode-island/retainage/ | Rhode Island's rows now state that the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and that a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier; the page had covered public work only and omitted the 60-day wait. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. | |
| /states/oklahoma/retainage/ | Oklahoma's public-work row now states the November 1, 2022 rule in 61 O.S. §§ 113.1 and 226: retainage is reduced to 2.5% of the amount earned to date after 50% completion with satisfactory progress; it had described the earlier rule limited to bonded work. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. | |
| /states/montana/retainage/ | Montana's public-work row now cites Mont. Code Ann. § 18-2-316, which caps retainage at 5% on state and local public contracts, and the 30-day final payment on building contracts in § 18-2-306; it had relied on a statute whose definition does not reach the state. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. | |
| /states/delaware/retainage/ | Delaware's public-work row now states the 60-day payment of retainage after completion or notice of completion, with interest from the 61st day, in 29 Del. C. § 6516(f)(3)-(4); it had no release deadline. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. | |
| /states/retainage-laws/ | The District of Columbia row now states the 10% retent on District construction contracts in D.C. Code § 2-203.01 and the private Prompt Payment Act, which counts retainage as an undisputed amount due on its schedule (§§ 27A-101 to 27A-104); both rows had said no statute applied. | Found in a 51-state re-check of the retainage table against current statutes; read on the official code site on 2026-10-17. |