Who this applies to
Whether the project is public or private makes no difference to the owner's duty in Tennessee. Section 66-34-103(b) is addressed to the owner "whether public or private" [1], which puts a public job and a private one on the same release schedule. The private and public sides of the rule carry identical terms: the same 90-day [1] release, the same 10-day [1] pass-down, the same 5% [1] ceiling at each tier and the same escrow requirement. The one difference is the price of skipping escrow, which public owners do not pay (see below).
Tennessee's retainage rules come in three parts:
- Owner and prime contractor. Under § 66-34-203, as Public Chapter 749 rewrote it, the owner may withhold a reasonable amount of retainage as the written contract specifies, as long as it does not exceed 5% of the amount of the contract [1]. The owner releases and pays retainage for completed work within 90 days [1].
- Prime contractor and remote contractors. The prime pays each remote contractor, to use the statute's term, the retainage due to it within 10 days [1] of receiving the owner's payment.
- The size of the holdback below the prime. Under § 66-34-303, as amended by Public Chapter 749 of 2020 [1], retainage between a prime contractor and a remote contractor may not exceed 5% of the contract amount [1].
What the rule says
Two events can start the owner's clock: completion of the work, and substantial completion of the project for the work completed. Whichever occurs first, the owner then has 90 days [1] to release and pay the prime all retainage for work completed under the contract. The prime's deadline is keyed to cash rather than to the job: its 10 days [1] begin when the owner's retainage payment is received, not at completion.
Tennessee also regulates where the money sits while it is held. Under § 66-34-104, retained funds must be deposited in a separate escrow account that bears interest and is held by a third party [1]. That section applies when the prime contract is $500,000 or more, whatever the size of the subcontracts, and it cannot be waived by contract [1]. On private work, a failure to deposit has a daily price, set out below.
How to comply
- Read the release clause in the prime contract against the 90-day [1] limit, and identify which triggering event, completion of the work or substantial completion of the project, will come first on your job.
- At both levels, owner to prime and prime to subcontractor, compare the stated retainage percentage with 5% [1] of the contract amount.
- For a remote contractor waiting on retainage, the date that matters is the day the prime receives the owner's payment; the prime's 10 days [1] run from there.
- On a prime contract of $500,000 or more [1], ask how retained funds are being held. A party that fails to deposit them in the required interest-bearing escrow account owes the owner of the funds $300 per day as damages under § 66-34-104(c) [1], and the failure is also a Class A misdemeanor [1]. Neither applies to the state, counties, municipalities, school and education boards or other subdivisions of the state [1].
The contract, the amended code sections and a lawyer familiar with them are the final word on how these deadlines apply to a particular job.
What changed recently
In 2020, the 111th General Assembly passed Public Chapter 749 [1], which amended sections 66-34-103, 66-34-104, 66-34-203 and 66-34-303 of the Tennessee Code [1]. The 5% ceilings sit in § 66-34-203 (owner to prime) and § 66-34-303 (prime to remote contractor), and the 90-day release and the escrow requirement in the other two sections [1]. The act took effect July 1, 2020 and applies to contracts entered into, amended or renewed on or after that date [1].
Related
- Retainage calculator: work out the dollar amount behind a retainage percentage on any contract.
- Retainage laws by state: Tennessee's single public-and-private rule alongside the other states.