Retainage · Virginia

Virginia retainage law: 5% cap on public construction (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

In a Virginia public construction contract with progress payments based on estimated percentage of completion, the contractor must be paid at least 95% of the earned sum, so no more than 5% is retained (Va. Code § 2.2-4333); subcontracts on public projects follow the same rule, and withheld sums may go into the final payment. No statewide statute governs private retainage; § 11-4.6 leaves it to the contract.

Private work

Virginia · Private workVerified 2026-09-22
Retainage cap
No statewide statute
Virginia's private construction payment statute (Sec. 11-4.6, the 2022 'SB 550' payment-terms law) expressly leaves retainage alone: its 60-day payment requirement neither applies to nor prohibits retainage provisions. No statewide cap or release deadline for retainage on private work was located.
Deadline
No statewide statute
What the statute says
Nothing in this subdivision shall be construed to apply to or prohibit the inclusion of any retainage provisions in a construction contract.
Va. Code Sec. 11-4.6. · Official text · retrieved 2026-09-22

Public work

Virginia · Public workVerified 2026-09-22
Retainage cap
5%
Public contracts for construction with progress payments based on estimated percentage of completion: the contractor must be paid at least 95% of the earned sum, so no more than 5% may be retained. The same rule flows down to subcontracts on public projects.
Deadline
The statute sets no separate release date; it states that all amounts withheld may be included in the final payment. For local-government contracts of $200,000 or more for the listed infrastructure work, the bid proposal must offer an escrow-account procedure for the retainage, with the escrow agreement due within 15 calendar days after notification.
What the statute says
In any public contract for construction that provides for progress payments in installments based upon an estimated percentage of completion, the contractor shall be paid at least ninety-five percent of the earned sum when payment is due, with no more than five percent being retained to ensure faithful performance of the contract.
Va. Code Sec. 2.2-4333. · Official text · retrieved 2026-09-22

Who this applies to

Virginia sets a retainage limit for public construction and leaves private construction to the parties.

Public projects. Section 2.2-4333 reaches any public contract for construction that pays in installments based on an estimated percentage of completion [1]. Subcontracts on public projects are held to the same limit as the prime contract.

Section 2.2-4334 adds an escrow option for some local-government work [2]. When a local-government contract of $200,000 or more [2] is for highways, roads, streets, bridges, parking lots, demolition, clearing, grading, excavating, paving, pile driving, drainage structures, or water, gas and sewer lines and pumping stations, the bid proposal must offer an escrow-account procedure for the retainage.

Private projects. No statewide statute fixes a retainage percentage or a release date for private construction in Virginia, so the contract controls both. Section 11-4.6, the 2022 "SB 550" payment-terms law, stays out of the question in so many words: its 60-day payment requirement neither applies to nor prohibits retainage provisions in a construction contract [3].

What the rule says

Section 2.2-4333 starts from the payment side [1]. When a progress payment falls due, the contractor must receive at least 95% of the earned sum [1], which means no more than 5% [1] may be retained, and the statute gives the purpose of that holdback as ensuring faithful performance of the contract. The section sets no separate deadline for giving it back; it says only that all amounts withheld may be included in the final payment.

For private work, what matters about § 11-4.6 is what it leaves out [3]. Interest penalties under § 2.2-4355 apply to late payment of invoiced amounts under § 11-4.6 [3], but the subsection that sets those payment terms is carved out from retainage, so the penalties do not reach retainage.

How to comply

For a public contract:

For a private contract, the retainage clause is the rule that applies. Its percentage and its release terms are whatever the parties wrote, and the payment-terms penalty in § 11-4.6 does not reach retainage [3].

What changed recently

Section 2.2-4333 began as § 11-56, enacted in 1982 (chapter 647), and was recodified into the Virginia Public Procurement Act in 2001 (chapter 844) [1]. Section 11-4.6's history is more recent and more crowded: 2020 (chapter 1038), a 2021 special session (chapter 511), 2022 (chapters 726, 727 and 771), 2023 (chapters 675 and 676) and 2026 (chapter 1040) [3].

Related

Retainage laws: other states

Sources

  1. Va. Code Sec. 2.2-4333, Retainage on construction contracts (retrieved 2026-09-22)
  2. Va. Code Sec. 2.2-4334, Deposit of certain retained funds on certain contracts with local governments (retrieved 2026-09-22)
  3. Va. Code Sec. 11-4.6, Required contract provisions in construction contracts (retrieved 2026-09-22)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.