Retainage · Nebraska

Nebraska retainage law: 10% cap, 45-day release (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Nebraska's Construction Prompt Pay Act caps retainage at the contract's figure, up to 10% (§ 45-1204). Once a contractor's or subcontractor's scope is 50% complete and it has performed and gives assurances, at most 5% of later progress payments may be held. The owner releases retainage for work done per the contract within 45 days after substantial completion (§ 45-1203). State of Nebraska contracts are excluded.

Private work

Nebraska · Private workVerified 2026-09-22
Retainage cap
10%
Retainage may not exceed the amount stated in the contract and in no case a rate of 10%. The cap and the step-down at 50% completion are in Neb. Rev. Stat. § 45-1204; the 45-day release and the 10-day pass-down to subcontractors are in the companion § 45-1203.
Deadline
45 days
Substantial completion of the project or a designated portion of it. Separately, once the withheld party's scope of work is 50% complete and it has performed in accordance with the contract, no more than 5% of any additional progress payment may be withheld if it gives satisfactory and reasonable assurances of continued performance and financial responsibility.
What the statute says
For retainage, in an amount not to exceed the amount specified in the applicable contract, which shall not exceed a rate of ten percent. If the scope of work for the contractor or subcontractor from which retainage is withheld is fifty percent complete ... no more than five percent of any additional progress payment may be withheld as retainage ...
Neb. Rev. Stat. § 45-1204 (cap) and § 45-1203 (release), Nebraska Construction Prompt Pay Act. · Archived copy of the official text, captured 2025-11-15

Public work

Nebraska · Public workVerified 2026-09-22
Retainage cap
10%
Retainage may not exceed the amount stated in the contract and in no case a rate of 10%. The Act reaches political subdivisions but expressly excludes contracts for the State of Nebraska and federal-aid or state-aid projects of a political subdivision on which the state pays the contractor, so State of Nebraska contracts are outside it. The cap and the step-down at 50% completion are in Neb. Rev. Stat. § 45-1204; the 45-day release and the 10-day pass-down to subcontractors are in the companion § 45-1203.
Deadline
45 days
Substantial completion of the project or a designated portion of it. Separately, once the withheld party's scope of work is 50% complete and it has performed in accordance with the contract, no more than 5% of any additional progress payment may be withheld if it gives satisfactory and reasonable assurances of continued performance and financial responsibility.
What the statute says
For retainage, in an amount not to exceed the amount specified in the applicable contract, which shall not exceed a rate of ten percent. If the scope of work for the contractor or subcontractor from which retainage is withheld is fifty percent complete ... no more than five percent of any additional progress payment may be withheld as retainage ...
Neb. Rev. Stat. § 45-1204 (cap) and § 45-1203 (release), Nebraska Construction Prompt Pay Act. · Archived copy of the official text, captured 2025-11-15

Who this applies to

A single statute, the Nebraska Construction Prompt Pay Act, governs retainage on private jobs and on local public work, and its figures are the same for both [4].

Its limits protect the tiers below the owner as well. The percentage rules are written about retainage withheld from a contractor or a subcontractor [4], and once a contractor receives retainage, its subcontractors are due their share within 10 days of that receipt [5].

On the public side, the Act reaches counties, cities and other political subdivisions [3]. Two kinds of public work are outside it [3]:

Those contracts fall outside this page; their retainage terms are a question for the contract itself, read with a lawyer.

What the rule says

The cap works in two stages, and release is tied to one event. Retainage may not exceed the amount the contract specifies, and in no case a rate of 10% [4]. When the withheld party's scope of work is 50% complete and it has performed in accordance with the contract, no more than 5% of each further progress payment may be held, provided that party gives satisfactory and reasonable assurances of continued performance and financial responsibility [4]. All retainage for work completed in accordance with the contract must then be released and paid within 45 days after the project, or a designated portion of it, is substantially complete [5].

How to comply

Both sections are linked under Sources; compare their wording with your contract and any subcontract before relying on these figures.

What changed recently

The session laws listed for these provisions are Laws 2010, LB552, § 4, and Laws 2014, LB961, § 7 [4].

Related

Retainage laws: other states

Sources

  1. Neb. Rev. Stat. 45-1204, Withholdings; authorized (Nebraska Legislature official page) (archived copy, captured 2025-11-15)
  2. Neb. Rev. Stat. 45-1203 (official page) (archived copy, captured 2026-01-17)
  3. Neb. Rev. Stat. 45-1202, Terms, defined (official page) (archived copy, captured 2026-01-23)
  4. Neb. Rev. Stat. § 45-1204 (retainage cap; 50% step-down), Nebraska Legislature (archived copy, captured 2025-11-15)
  5. Neb. Rev. Stat. § 45-1203 (release of retainage; 45 days), Nebraska Legislature (archived copy, captured 2026-01-17)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.