Wisconsin retainage law: 5% until 50% done on local public work (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Under Wis. Stat. § 66.0901(9)(b), retainage on a local public contract may be no more than 5% of the estimate until 50% of the work is complete. After that, partial payments are made in full and nothing more is held unless the architect or engineer certifies the job is not proceeding satisfactorily; total retainage is then capped at 10% of the value of work completed. Retainage may be paid on substantial completion.

Private work

Wisconsin · Private workVerified 2026-09-22
Retainage cap
Not in our verified record
Deadline
Not in our verified record
Statute
Not in our verified record

Public work

Wisconsin · Public workVerified 2026-09-22
Retainage cap
5%
Wis. Stat. § 66.0901(9)(b) limits retainage to an amount equal to not more than 5 percent of the estimate until 50 percent of the work has been completed. At 50 percent completion further partial payments are made in full and no additional amounts may be retained unless the architect or engineer certifies that the job is not proceeding satisfactorily, in which case the total retainage may not be more than 10 percent of the value of the work completed.
Deadline
Retainage may be paid on substantial completion; the section sets no day-count deadline.
What the statute says
The retainage shall be an amount equal to not more than 5 percent of the estimate until 50 percent of the work has been completed. At 50 percent completion, further partial payments shall be made in full to the contractor and no additional amounts may be retained unless the architect or engineer certifies that the job is not proceeding satisfactorily
Wis. Stat. § 66.0901(9)(b). · Archived copy of the official text, captured 2025-11-19

Who this applies to

This page covers a single rule: the retainage limit in Wis. Stat. § 66.0901(9)(b), part of the statute on public contracts [2]. It applies on local public construction contracts. The section deals with the partial payments made to the contractor while the work is under way, and with how much of each payment may be kept back.

Private construction sits outside what this page covers. On a private job, the contract states the retainage terms, and a lawyer is the person to say whether anything beyond the contract applies. The same holds for retainage a contractor keeps from its subcontractors: the section's wording is about partial payments to the contractor, so the subcontract and a lawyer answer those questions.

What the rule says

The public rule divides the job at its halfway point.

First phase. Until 50% [2] of the work has been completed, retainage may be an amount equal to no more than 5% [2] of the estimate.

Second phase. From 50% [2] completion onward, further partial payments go to the contractor in full, and no additional amounts may be retained. The exception is a certification by the architect or engineer that the job is not proceeding satisfactorily. With that certification, retainage can resume, but the total held may not be more than 10% [2] of the value of the work completed.

The two figures are measured against different bases. The 5% [2] applies to the estimate, while the 10% [2] ceiling applies to the value of the work completed.

At the end of the job, retainage may be paid on substantial completion. The section does not attach a number of days to that payment.

How to comply

Related

Retainage laws: other states

Sources

  1. Wisconsin DOT AASHTOWare Project Knowledge Base, 'Retainage' (agency practice, not statutory text) (retrieved 2026-09-22)
  2. Wis. Stat. § 66.0901(9) (public contracts; retainage), Wisconsin Legislature (archived copy, captured 2025-11-19)
  3. Wis. Stat. ch. 779, official chapter PDF (§ 779.135, void contract provisions), Wisconsin Legislature (archived copy, captured 2026-07-13)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.