Retainage · Oklahoma

Oklahoma retainage law: 5% public cap, 21-day release (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Oklahoma's Title 61 retainage statutes reach only government owners, so private retainage is set by the contract. On public construction, 61 O.S. § 113.1 allows up to 5% of partial payments, and the Fair Pay for Construction Act (61 O.S. § 226) lowers the rate to 2.5% on bonded work at least 50% complete. The owner releases retainage within 21 calendar days of a certificate of substantial completion.

Private work

Oklahoma · Private workVerified 2026-09-22
Retainage cap
No statewide statute
No Oklahoma retainage statute reaching private owners was located. Both retainage regimes found in Title 61 are public: 61 O.S. § 113.1 governs 'a public construction contract', and the Fair Pay for Construction Act (61 O.S. §§ 221-227) defines 'Owner' as 'any state government entity, municipality, township, public trust or an instrumentality of a state government entity, municipality, township or public trust in this state'.
Deadline
No statewide statute
Statute
No statewide statute

Public work

Oklahoma · Public workVerified 2026-09-22
Retainage cap
5%
Two overlapping regimes. 61 O.S. § 113.1: a public construction contract shall provide that up to 5% of all partial payments is withheld as retainage; the Department of Transportation and the Oklahoma Turnpike Authority may not withhold retainage at all. Fair Pay for Construction Act, 61 O.S. § 226: retainage not to exceed 5% of the payment due, dropping to 2.5% on the balance of the work where the contract is bonded under Title 61 and the work is at least 50% complete; the same applies to subcontracts. The Act does not apply to highway, railroad or turnpike construction, to roads, bridges, utilities, traffic control, drainage, sanitary sewer or waterline construction except as part of a construction contract, or to one- to four-family dwellings.
Deadline
21 days
Issuance of a certificate of substantial completion for the project or a separate usable phase, with adequate performance by the prime contractor and approval of any applicable surety.
What the statute says
A public construction contract shall provide for partial payment based upon work completed. The contract shall provide that up to five percent (5%) of all partial payments made shall be withheld as retainage.
61 O.S. § 113.1 and 61 O.S. § 226 (Fair Pay for Construction Act). · Official text · retrieved 2026-09-22

Who this applies to

Oklahoma's retainage statutes in Title 61 are written for government owners only [1]. Section 113.1 of Title 61 governs "a public construction contract," and the Fair Pay for Construction Act defines "Owner" as a state government entity, municipality, township or public trust, or an instrumentality of one of them [1]. Neither statute reaches private construction, so on a private job the percentage and the release date are whatever the contract provides.

On public jobs, two statutes overlap [1]:

What the rule says

Both public statutes start from a 5% ceiling [1], and the Act adds a lower tier: where the contract is bonded under Title 61 and the work is at least 50% complete, retainage on the balance of the work may not exceed 2.5% [1]. Release is keyed to a certificate of substantial completion for the project or a separate usable phase. Within 21 calendar days after it issues, provided the prime contractor has performed adequately and any applicable surety approves, the owner releases retainage to the prime contractor, keeping back no more than 150% of the estimated costs to correct any incomplete or defective work [1].

How to comply

The statute text is linked under Sources. On a private job, the contract is the document that answers each of these questions.

What changed recently

Section 113.1 was added by Laws 1977, c. 74, § 2, and amended by Laws 2011, c. 99, § 1, effective November 1, 2011 [1]. Section 226 of the Fair Pay for Construction Act was added by Laws 2004, c. 256, § 6, and amended by Laws 2019, c. 456, § 1, effective November 1, 2019 [1].

Related

Retainage laws: other states

Sources

  1. Oklahoma Statutes, Title 61, Public Buildings and Public Works (Oklahoma State Senate official publication), §§ 113.1, 113.2, 113.3, 221-227 (retrieved 2026-09-22)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.