Retainage · New York

New York retainage law: 5% cap, 30-day release (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

New York's General Business Law § 756-c lets a private owner retain no more than 5% of the contract sum by mutual agreement, keeps lower tiers at or below the owner's percentage, and requires release within 30 days after final approval, with 1% a month interest if late. Public owners under General Municipal Law § 106-b retain up to 5% of each progress payment, or up to 10% if they do not require both full bonds.

Private work

New York · Private workVerified 2026-09-22
Retainage cap
5%
By mutual agreement an owner may retain no more than 5% of the contract sum; a contractor or subcontractor may also retain no more than 5%, and in no case more than the percentage the owner actually retains.
Deadline
30 days
Final approval of the work under the construction contract.
What the statute says
By mutual agreement of the relevant parties an owner may retain no more than five per centum of the contract sum as retainage. A contractor or subcontractor may also retain no more than five per centum for retainage and in no case shall retainage exceed the actual percentage retained by the owner.
N.Y. Gen. Bus. Law § 756-c (Prompt Payment Act, art. 35-E). · Official text · retrieved 2026-09-22

Public work

New York · Public workVerified 2026-09-22
Retainage cap
5%
A public owner retains not more than 5% of each progress payment, but may retain more than 5% and up to 10% if it does not require the contractor to furnish both a performance bond and a labor and material bond in the full amount of the contract. A contractor may retain the same percentages from subcontractors.
Deadline
Substantial completion: within 45 business days of substantial completion the public owner submits a written punch list, then approves and pays the remaining contract balance less two times the value of any remaining items to be completed; as those items are completed the owner promptly pays for them on requisition.
What the statute says
The public owner shall retain not more than five per centum of each progress payment to the contractor except that the public owner may retain in excess of five per centum but not more than ten per centum of each progress payment to the contractor provided that there are no requirements by the public owner for the contractor to provide a performance bond and a labor and material bond both in the full amount of the contract.
N.Y. Gen. Mun. Law § 106-b. · Official text · retrieved 2026-09-22

Who this applies to

This page covers two New York retainage laws, one for private construction and one for public owners.

The private rule is § 756-c of the General Business Law, part of the Prompt Payment Act in article 35-E [1]. It binds every tier of the chain: an owner retaining from its contractor, and a contractor or subcontractor retaining from the party below it [1].

The public rule is § 106-b of the General Municipal Law, which covers political subdivisions as public owners; a contractor may withhold the same percentages from its subcontractors [2]. Construction contracts of state agencies are not covered on this page.

What the rule says

The private cap is measured against the contract sum and rests on the parties' agreement: by mutual agreement an owner may retain no more than 5% of it, and a contractor or subcontractor may retain no more than 5% and in no case more than the percentage the owner actually retains [1]. The public cap is measured against each progress payment instead: not more than 5%, rising to at most 10% only where the public owner does not require the contractor to furnish both a performance bond and a labor and material bond in the full amount of the contract [2]. Neither percentage steps down during the job [1] [2].

How to comply

Private contracts

Public contracts

Both sections are linked under Sources. On a private job the contract and subcontract fix the percentage within the cap; on a public job the bond requirements decide which ceiling applies.

What changed recently

General Business Law § 756-c was amended on November 26, 2023 [1]. General Municipal Law § 106-b was last amended on June 18, 2021 [2].

Related

Retainage laws: other states

Sources

  1. N.Y. General Business Law § 756-c, Retention, New York State Senate official law page (retrieved 2026-09-22)
  2. N.Y. General Municipal Law § 106-b, New York State Senate official law page (retrieved 2026-09-22)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.