Retainage · Missouri

Missouri retainage law: 5% public-works cap, 30-day release (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

No Missouri statute sets a retainage rule for private work; § 431.180 only requires payments on the contract's schedule. On public works, § 8.960 caps retainage at 5% of the contract or subcontract, or 10% where no bond is required under § 107.170. The public owner pays at least 98% of retainage within 30 days after acceptance, once the invoice and documentation are complete; late payment carries 1.5% per month.

Private work

Missouri · Private workVerified 2026-09-22
Retainage cap
No statewide statute
Missouri's private construction payment statute, § 431.180, requires only that scheduled payments be made according to the contract; it contains no retainage cap, no release deadline and no retainage-specific rule. It does not apply to contracts for building, improving, repairing or remodeling owner-occupied residential property of four units or less. Missouri's retainage rules (§ 8.960) are limited by their terms to public works contracts awarded by the state, a political subdivision or a district.
Deadline
No statewide statute
What the statute says
All persons who enter into a contract for private design or construction work after August 28, 1995, shall make all scheduled payments pursuant to the terms of the contract.
Mo. Rev. Stat. § 431.180 (no retainage provision). · Official text · retrieved 2026-09-22

Public work

Missouri · Public workVerified 2026-09-22
Retainage cap
5%
'Retainage withheld on any construction contract or subcontract for public works projects shall not exceed five percent of the value of the contract or subcontract.' Where no bond is required under § 107.170 because the contract is not estimated to exceed $50,000, the public owner may withhold up to 10%. A public owner may reduce or eliminate retainage on any payment if the work is proceeding satisfactorily, and where a subcontractor's work is complete the contractor may request an adjustment so the sub can be paid in full before substantial completion.
Deadline
30 days
The public owner must pay at least 98% of the retainage, less authorized offsets, and payment to the subcontractor or supplier follows substantial completion of the contract work and acceptance by the public owner's authorized contract representative; that payment is due within 30 days after acceptance once the invoice and required documentation are in complete and acceptable form. If the owner decides the work is not substantially complete and accepted, it must give a written explanation within 14 calendar days; if it does not, it must pay at least 98% of the retainage within 30 calendar days. Where minor items remain, 150% of the value of each item may be withheld until completed. Final payment of all money owed, including retainage, is due within 30 days of the due date.
What the statute says
Retainage withheld on any construction contract or subcontract for public works projects shall not exceed five percent of the value of the contract or subcontract. If the contractor is not required to obtain a bond under section 107.170… the public owner may withhold retainage on the public works project in an amount not to exceed ten percent of the value of the contract or subcontract.
Mo. Rev. Stat. § 8.960 (formerly § 34.057). · Official text · retrieved 2026-09-22

Who this applies to

Missouri's retainage rules are confined to public works. Section 8.960 is limited by its terms to public works contracts awarded by the state, a political subdivision or a district [1], and it reaches both the prime contract and the subcontracts beneath it [1]. This page does not cover highway, road and bridge projects administered by the state highways and transportation commission; for those, read § 8.960 [1] together with the contract.

Private jobs are a different story. No statewide statute sets a retainage cap, a release deadline or any other retainage rule for private construction, so the contract between the parties governs the amount held and when it comes back [2]. The private payment statute, § 431.180, requires only that everyone who entered into a contract for private design or construction work after August 28, 1995 make all scheduled payments under its terms [2]. That statute does not apply to contracts for building, improving, repairing or remodeling owner-occupied residential property of four units or less [2].

What the rule says

On a public works project, retainage on a construction contract or subcontract may not exceed 5% of the value of that contract or subcontract [1]. A higher limit applies where the contractor is not required to obtain a bond under § 107.170 because the contract is not estimated to exceed $50,000: there the public owner may withhold up to 10% [1]. The owner may also reduce or eliminate retainage on any payment while the work is proceeding satisfactorily [1]. When a subcontractor's work is complete, the contractor may request an adjustment so that subcontractor can be paid in full before substantial completion [1].

How to comply

On public work, the release runs in this order.

  1. Substantial completion and acceptance. Payment follows substantial completion of the contract work and acceptance by the public owner's authorized contract representative [1].
  2. A written answer within 14 calendar days. If the owner decides the work is not substantially complete and accepted, it must explain why in writing within 14 calendar days [1]. If it does not, it must pay at least 98% of the retainage within 30 calendar days [1].
  3. Payment within 30 days. The owner pays the contractor at least 98% of the retainage, less offsets or deductions authorized in the contract or by law, within 30 days after acceptance, once the invoice and required documentation are in complete and acceptable form [1].
  4. Punch-list items. Where minor items remain, the owner may withhold 150% of the value of each item until it is completed [1].
  5. Passing payment down. A contractor that, without reasonable cause, fails to pay its subcontractors and suppliers within 15 days of being paid owes them 1.5% per month, and that rule applies at every tier [1].

If the contracting agency misses the 30-day progress-payment window, it owes 1.5% per month from the end of that period until paid [1]. Money withheld in good faith for reasonable cause earns no interest [1]. If a court finds a withholding was not in good faith, it may impose 1.5% per month from the invoice date and award attorney fees [1].

On private work, check the retainage clause of the contract itself. If a party is not paid as the contract provides, it may sue under § 431.180, and the court may award interest of up to 1.5% per month from the date payment was due plus reasonable attorney fees to the prevailing party [2]. An arbitrator under § 435.350 may award the same remedies [2]. That is a general non-payment remedy rather than a retainage rule.

What changed recently

Missouri's public retainage section was transferred in 2022 from § 34.057 to § 8.960 [3], and its history lists L. 2022 S.B. 758, effective 28 August 2022 [1]. The private payment statute, § 431.180, comes from S.B. 93 of 1995 and was amended by H.B. 343 of 1999, effective 28 August 1999 [2].

Related

Retainage laws: other states

Sources

  1. Mo. Rev. Stat. § 8.960, Prompt payments required, progress payments, retainage, late payment charges, withholding of payments (Missouri Revisor of Statutes) (retrieved 2026-09-22)
  2. Mo. Rev. Stat. § 431.180, Contract for private design or construction work, scheduled payments (Missouri Revisor of Statutes) (retrieved 2026-09-22)
  3. Mo. Rev. Stat. § 34.057, Transferred 2022; now § 8.960 (Missouri Revisor of Statutes) (retrieved 2026-09-22)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.