Who this applies to
Missouri has two retainage statutes, one for each side. Section 8.960 is limited by its terms to public works contracts awarded by the state, a political subdivision or a district [1], and it reaches both the prime contract and the subcontracts beneath it [1]. This page does not cover highway, road and bridge projects administered by the state highways and transportation commission; for those, read § 8.960 [1] together with the contract.
Private jobs fall under §§ 436.300 to 436.336, which apply to contracts entered into after August 28, 2002 on all private construction projects except single-family residential construction and other residential construction of four or fewer units [4]. A contract formed after that date is unenforceable to the extent it conflicts with them [4]. Separately, § 431.180 requires everyone who entered into a contract for private design or construction work after August 28, 1995 to make all scheduled payments under its terms [2].
What the rule says
On a public works project, retainage on a construction contract or subcontract may not exceed 5% of the value of that contract or subcontract [1]. A higher limit applies where the contractor is not required to obtain a bond under § 107.170 because the contract is not estimated to exceed $50,000: there the public owner may withhold up to 10% [1]. The owner may also reduce or eliminate retainage on any payment while the work is proceeding satisfactorily [1]. When a subcontractor's work is complete, the contractor may request an adjustment so that subcontractor can be paid in full before substantial completion [1].
On a private project, a contract may provide for retainage of no more than 10% of any payment due from the owner to the contractor, and the owner holds it in trust for the contractor and its subcontractors and suppliers at every tier who are not in default [4]. If the contractor's performance does not follow the contract, the contract may let the owner retain more [4]. A contractor may not withhold from a subcontractor more retainage than the owner withholds from the contractor for that subcontractor's work, unless the subcontractor's own performance falls short [4].
How to comply
On public work, the release runs in this order.
- Substantial completion and acceptance. Payment follows substantial completion of the contract work and acceptance by the public owner's authorized contract representative [1].
- A written answer within 14 calendar days. If the owner decides the work is not substantially complete and accepted, it must explain why in writing within 14 calendar days [1]. If it does not, it must pay at least 98% of the retainage within 30 calendar days [1].
- Payment within 30 days. The owner pays the contractor at least 98% of the retainage, less offsets or deductions authorized in the contract or by law, within 30 days after acceptance, once the invoice and required documentation are in complete and acceptable form [1].
- Punch-list items. Where minor items remain, the owner may withhold 150% of the value of each item until it is completed [1].
- Passing payment down. A contractor that, without reasonable cause, fails to pay its subcontractors and suppliers within 15 days of being paid owes them 1.5% per month, and that rule applies at every tier [1].
If the contracting agency misses the 30-day progress-payment window, it owes 1.5% per month from the end of that period until paid [1]. Money withheld in good faith for reasonable cause earns no interest [1]. If a court finds a withholding was not in good faith, it may impose 1.5% per month from the invoice date and award attorney fees [1].
On private work, the release runs this way.
- Substantial completion. The project reaches substantial completion at the earlier of the architect's or engineer's certificate of substantial completion or the owner's acceptance of the full contract [4].
- Release within 30 days. Within 30 days of substantial completion, the owner releases all retainage or substitute security to the contractor, less 150% of the cost to complete any remaining items [4].
- Passing it down. The contractor releases each subcontractor's share within 7 days of receiving it [4].
- If it is withheld wrongly. A court may award interest of up to 1.5% per month from the date of the wrongful withholding, on top of other damages, and reasonable attorney's fees to the prevailing party [4].
A party not paid on the contract's schedule also has the general remedy in § 431.180: interest of up to 1.5% per month from the date payment was due and attorney fees [2].
What changed recently
Missouri's public retainage section was transferred in 2022 from § 34.057 to § 8.960 [3], and its history lists L. 2022 S.B. 758, effective 28 August 2022 [1]. The private retainage sections, §§ 436.300 to 436.336, come from H.B. 1403 of 2002, effective 28 August 2002, with no later amendment [4]. The general private payment statute, § 431.180, comes from S.B. 93 of 1995 and was amended by H.B. 343 of 1999, effective 28 August 1999 [2].
Related
- Retainage calculator: pay-application retainage and payment due, with a public-project setting.
- Retainage laws by state: the rules for public and private work elsewhere.