Retainage · Texas

Texas retainage law: 10% or 5% public cap, 10% owner reserve (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

A Texas governmental entity may withhold no more than 10% of the contract price on a public works contract under $5 million, 5% at $5 million or more, and 10% on dam work (Gov't Code § 2252.032), and may not hold retainage once the work is complete. Private contracts set their own retainage rate, but the owner must reserve 10% for lien claimants during the work and for 30 days after completion (Prop. Code § 53.101).

Private work

Texas · Private workVerified 2026-09-22
Retainage cap
Texas does not cap contractual retainage on private work. The statute instead requires the owner to reserve 10% of the contract price (or 10% of the value of work done) as a fund for lien claimants during the work and for 30 days after completion. Subchapter E was rewritten by H.B. 2237 (2021) and is now titled 'Funds Reserved for Benefit of Lien Claimants.'
Deadline
The owner's duty to reserve runs during the progress of the work and for 30 days after the work under the original contract is completed; a claimant must file a lien affidavit on the reserved funds not later than the 30th day after completion, termination, or abandonment (Sec. 53.103).
What the statute says
During the progress of work under an original contract for which a mechanic's lien may be claimed and for 30 days after the work under the contract is completed, the owner shall reserve: (1) 10 percent of the contract price of the work to the owner; or (2) 10 percent of the value of the work...
Tex. Prop. Code Sec. 53.101. · Archived copy of the official text, captured 2025-08-13

Public work

Texas · Public workVerified 2026-09-22
Retainage cap
10%
Two-tier cap set by H.B. 692 (2021): 10% if the public works contract is worth less than $5 million; 5% if it is $5 million or more; 10% for dam construction or maintenance regardless of value. The cap also limits the rate for any single line item in the bid schedule or schedule of values, including materials and equipment delivered on site. Subchapter B does not apply to contracts under $400,000, contracts executed before Aug. 31, 1981, or TxDOT contracts under Transportation Code ch. 223.
Deadline
Completion of the work required under the contract: the entity may not hold retainage after completion, including during the warranty period, and must pay remaining retainage plus interest earned on completion. Retainage may still be withheld on final application only for a bona fide dispute over noncompliant labor, services or materials, or if the surety will not agree to release.
What the statute says
(1) if the total value of a public works contract is less than $5 million, a governmental entity may not withhold retainage in an amount that exceeds 10 percent of the contract price ... (2) if the total value of a public works contract is $5 million or more, a governmental entity may not withhold retainage in an amount that exceeds five percent of the contract price
Tex. Gov't Code Sec. 2252.032. · Archived copy of the official text, captured 2025-12-18

Who this applies to

Texas handles public and private retainage with two statutes that do different jobs. The Government Code limits what a governmental entity may hold back from a contractor. Texas does not cap contractual retainage on private work at all; the Property Code instead makes the owner set money aside for lien claimants.

Public works. Section 2252.032 of the Government Code sets the limits [2]. Its subchapter does not reach contracts under $400,000, contracts executed before Aug. 31, 1981, or TxDOT contracts under chapter 223 of the Transportation Code [2]. Where it applies, subcontractors may not be held to a higher retainage percentage than the prime contractor [2].

Private work. The duty to reserve attaches to an original contract for which a mechanic's lien may be claimed, and it falls on the owner [1]. The rate of retainage in the contract itself is for the parties to set.

What the rule says

On public work, the ceiling depends on the contract's total value:

The same ceiling applies to each line item in the bid schedule or schedule of values, materials and equipment delivered on site included. The tier does not step down as the job progresses. Instead, the contract must state when the project is substantially complete and when the entity may release retainage on portions that are substantially complete or fully completed and accepted.

On private work, while the job is under way and for 30 days [1] after the work under the original contract is completed, the owner must reserve 10% of the contract price of the work, or 10% of the value of the work [1]. The subchapter holding this rule, Subchapter E, is titled "Funds Reserved for Benefit of Lien Claimants."

How to comply

On a public contract:

  1. Match the contract's total value to its tier, then compare the retainage clause, line items included, with that percentage.
  2. Once the prime contractor has completed the work the contract requires, the entity may not keep withholding retainage, not even during the warranty period, and for the contracts described in subsection (c) it pays the remaining retainage together with the interest earned on it.
  3. On the final application, retainage may still be withheld only for a bona fide dispute over noncompliant labor, services or materials, or where the surety will not agree to the release.
  4. On competitively awarded contracts of $10 million or more [2], and on contracts awarded without competition, the parties may agree to hold retainage in an interest-bearing account; certain water-project entities must deposit retainage above 5% [2] in one.

On a private job, the retainage percentage comes from the contract, and the owner's reserve runs alongside it. A claimant going after the reserved funds must file a lien affidavit on them no later than the 30th day after completion, termination or abandonment (§ 53.103) [1]. Subchapter E carries no interest or penalty; its sanction is lien exposure. An owner who fails to reserve faces a lien on the improvement and the land, in favor of claimants who comply with Subchapter C or E, at least to the extent of the amount that should have been reserved (§ 53.105) [1].

What changed recently

The public tiers come from H.B. 692, which amended § 2252.032 effective June 15, 2021 (Acts 2021, 87th Legislature, Regular Session, chapter 635, section 3) [2]; the section itself was added in 1993 by chapter 268 of the 73rd Legislature [2]. On the private side, H.B. 2237 rewrote Subchapter E, and its section 18 amended § 53.101 effective January 1, 2022 (Acts 2021, chapter 690) [1]. Section 53.101 traces to 1983 (68th Legislature, chapter 576) and was amended in 1989 [1].

Related

Retainage laws: other states

Sources

  1. statutes.capitol.texas.gov/Docs/PR/htm/PR.53.htm (archived copy, captured 2025-08-13)
  2. statutes.capitol.texas.gov/Docs/GV/htm/GV.2252.htm (archived copy, captured 2025-12-18)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.