Retainage · North Carolina

North Carolina retainage law: 5% public cap, 60-day release (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

On North Carolina public projects (G.S. 143-134.1(b1)), no retainage is allowed under $100,000 in total project costs; from $100,000 up it is capped at 5% of each periodic payment, released within 60 days after a pay request plus substantial completion or beneficial occupancy. No statute caps private retainage, but a contractor may not hold more from a subcontractor than the owner's initial percentage (G.S. 22C-4).

Private work

North Carolina · Private workVerified 2026-09-22
Retainage cap
No North Carolina statute caps retainage on private construction. The only statutory limit is a pass-through rule: under G.S. 22C-4 a contractor may withhold from a subcontractor 'a reasonable amount for retainage not to exceed the initial percentage retained by the owner'. Chapter 22C does not apply to residential contractors as defined in G.S. 87-10(1a), or to residential improvements of 12 or fewer units (G.S. 22C-6).
Deadline
7 days
The contractor's receipt of each periodic or final payment from the owner. The seven-day deadline is for paying subcontractors; Chapter 22C sets no date for the owner's release of retainage.
What the statute says
Nothing in this Chapter shall prevent the contractor ... from withholding such application and certification to the owner for payment to the subcontractor for: ... or a reasonable amount for retainage not to exceed the initial percentage retained by the owner.
N.C. Gen. Stat. ch. 22C (Payments to Subcontractors), §§ 22C-3, 22C-4, 22C-5, 22C-6. · Archived copy of the official text, captured 2026-08-03

Public work

North Carolina · Public workVerified 2026-09-22
Retainage cap
5%
No retainage at all is allowed where total project costs are under $100,000. At or above $100,000 the owner may not retain more than 5% of any periodic payment. Applies to public construction contracts let by the State or any political subdivision, except contracts let by the Department of Transportation under G.S. 136-28.1.
Deadline
60 days
Submission of a pay request plus either the owner's receipt of a certificate of substantial completion from the architect/engineer/designer, or the owner's beneficial occupancy or use of the project.
What the statute says
The owner shall not retain more than five percent (5%) of any periodic payment due a prime contractor. When the project is fifty percent (50%) complete, the owner, with written consent of the surety, shall not retain any further retainage from periodic payments due the contractor if the contractor continues to perform satisfactorily ...
N.C. Gen. Stat. § 143-134.1(b1). · Archived copy of the official text, captured 2025-03-18

Who this applies to

North Carolina treats the two sides very differently. Public work has a detailed retainage statute; private work has only rules for what passes from contractor to subcontractor.

Public construction. G.S. 143-134.1(b1) governs public construction contracts let by the State or any political subdivision [1]. Contracts let by the Department of Transportation under G.S. 136-28.1 are outside it [1].

Private construction. No North Carolina statute caps retainage on private work, so the amount an owner holds is a matter for the contract [2]. Chapter 22C, on payments to subcontractors, supplies the one statutory limit [2]. It does not apply to residential contractors as defined in G.S. 87-10(1a), or to residential improvements of 12 or fewer units [2].

What the rule says

Public retainage depends first on project size. Where total project costs are under $100,000, no retainage is allowed at all [1]. At $100,000 or more, the owner may not retain more than 5% of any periodic payment due a prime contractor [1]. Halfway through the job the withholding stops: once the project is 50% complete, the owner, with the surety's written consent, may not retain anything further from periodic payments while the contractor keeps performing satisfactorily [1]. After that 50% point, the owner may withhold additional retainage so that it holds 2.5% in total through completion [1]. On private jobs the only statutory ceiling sits one level down: a contractor may withhold from a subcontractor a reasonable amount for retainage, not exceeding the initial percentage the owner retained [2].

How to comply

Public projects, owner to prime contractor:

  1. Check whether total project costs reach $100,000, since below that figure no retainage applies [1].
  2. Compare each pay application's retainage with the 5% per-payment ceiling [1].
  3. At 50% completion, check the pay applications that follow against the surety-consent rule and the 2.5% total described above [1].
  4. Release comes within 60 days after a pay request is submitted and either the owner receives a certificate of substantial completion from the architect, engineer or designer in charge, or the owner receives beneficial occupancy or use of the project, as the contract documents specify [1]. The owner releases it with the surety's written consent, and may keep back no more than 2.5 times the value of the remaining work [1].
  5. For early finishing trades, retainage drops to 0.5% once that trade's work is 100% complete, with payment within 60 days [1].

Final payment delayed more than 45 days after acceptance, certification of completion, or occupancy and use bears interest from the 46th day at 1% per month or fraction thereof, though a lower agreed rate may apply [1]. Retainage a prime contractor holds from a subcontractor above the owner's percentage also bears 1% per month [1]. On bonded projects, bids may be taken both with and without retainage [1].

Private projects, contractor to subcontractor: When a subcontractor has performed under its contract, the contractor must pay it the full amount received for that subcontractor's work and materials within seven days of receiving each periodic or final payment, and each subcontractor owes the same to its own subcontractors [2]. That seven-day deadline is for paying subcontractors; Chapter 22C sets no date for the owner's release of retainage to the contractor [2]. A payment held more than seven days past receipt bears interest at 1% per month or fraction thereof on the unpaid balance, starting on the eighth day [2].

What changed recently

The public section, G.S. 143-134.1, dates from 1959, c. 1328, and its history lists changes in 1967, 1979, 1983 and 2007-365, s. 1 [1]. Check the current text of the section for any later amendment before relying on the public figures above. Chapter 22C dates from 1987 (Regular Session, 1988), c. 946, and its § 22C-2 was amended in 1991, c. 620 [2].

Related

Retainage laws: other states

Sources

  1. N.C. Gen. Stat. § 143-134.1, North Carolina General Assembly official statute page (archived copy, captured 2025-03-18)
  2. N.C. Gen. Stat. Chapter 22C, Payments to Subcontractors, North Carolina General Assembly official chapter page (archived copy, captured 2026-08-03)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.