Retainage · Rhode Island

Rhode Island retainage law: 5% cap, public and private (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Under R.I. Gen. Laws § 37-12-10.1, no contract for construction, or for state or municipal public works, may include retainage above 5% of any progress payment. A contract for construction (§ 5-65-1) is a lienable private job or public project of $250,000 or more, excluding homes of 1 to 4 units. A retainage application may follow 60 days after substantial completion and is paid within 30 days.

Private work

Rhode Island · Private workVerified 2026-09-22
Retainage cap
5%
R.I. Gen. Laws § 37-12-10.1(a) bars any contract for construction, as defined in § 5-65-1, from including retainage that exceeds five percent (5%) of any progress payment. A 'contract for construction' (§ 5-65-1(6)) is a contract for which a mechanics' lien may be established under chapter 28 of title 34, or for state or municipal public works, on a project whose original contract with the owner is at least $250,000; it does not include a project containing one to four dwelling units. So a private, lienable job of $250,000 or more is covered, and private homes of one to four units are not. Withholding on release is limited to 150% of the cost to complete plus 2.5% of the adjusted contract price, with 0.5% holdable for up to one year.
Deadline
30 days
Not earlier than 60 days after substantial completion (or the final resolution of a dispute), unless the contract provides for an earlier submission, a person may submit a written application for payment of retainage, which is paid within 30 days of submission; each tier below the owner may take 7 days longer than the tier above (§ 37-12-10.1(e)). Before that, the prime contractor gives notice of substantial completion within 14 days of reaching it, and the owner has 14 days to accept or reject (§ 37-12-10.1(b)-(c)).
What the statute says
(a) No contract for construction, as defined in Sec. 5-65-1, or for state or municipal public works projects, as defined in this title, excluding contracts under Sec. 37-12-10, shall include retainage that exceeds five percent (5%) of any progress payment.
R.I. Gen. Laws § 37-12-10.1, with the definition in § 5-65-1(6). · Archived copy of the official text, captured 2026-07-24

Public work

Rhode Island · Public workVerified 2026-09-22
Retainage cap
5%
R.I. Gen. Laws § 37-12-10.1(a) bars any contract for construction, as defined in § 5-65-1, or for state or municipal public works projects, from including retainage that exceeds five percent (5%) of any progress payment; contracts under § 37-12-10 are excluded. A 'contract for construction' (§ 5-65-1(6)) is a contract for which a mechanics' lien may be established under chapter 28 of title 34, or for state or municipal public works, on a project whose original contract with the owner is at least $250,000; it does not include a project containing one to four dwelling units. Withholding on release is limited to 150% of the cost to complete plus 2.5% of the adjusted contract price, with 0.5% holdable for up to one year. The Rhode Island Department of Transportation is exempt from § 37-12-10.1 and may deduct up to 5% of the contract price (§ 37-12-10.1(m)). The companion § 37-12-10 lets an awarding authority retain not exceeding five percent (5%) of the contract price on public works, sewer and water-main contracts under $500,000.
Deadline
30 days
Not earlier than 60 days after substantial completion (or the final resolution of a dispute), unless the contract provides for an earlier submission, a person may submit a written application for payment of retainage, which is paid within 30 days of submission; each tier below the owner may take 7 days longer than the tier above (§ 37-12-10.1(e)). Before that, the prime contractor gives notice of substantial completion within 14 days of reaching it, and the owner has 14 days to accept or reject (§ 37-12-10.1(b)-(c)).
What the statute says
(a) No contract for construction, as defined in Sec. 5-65-1, or for state or municipal public works projects, as defined in this title, excluding contracts under Sec. 37-12-10, shall include retainage that exceeds five percent (5%) of any progress payment.
R.I. Gen. Laws § 37-12-10.1. · Archived copy of the official text, captured 2026-07-24

Who this applies to

Section 37-12-10.1 of the Rhode Island General Laws reaches two kinds of contract: contracts for construction as defined in § 5-65-1, and contracts for state or municipal public works projects [1]. Contracts under § 37-12-10 are excluded from it [1].

A contract for construction is a contract for which a mechanics' lien may be established, or for state or municipal public works, on a project whose original contract with the owner is at least $250,000; a project containing one to four dwelling units is not one [2]. So the section reaches private, lienable jobs of that size as well as public works. The Rhode Island Department of Transportation is exempt from it, and may deduct up to 5% of the contract price instead [1].

The section speaks to three stages of a job: the retainage a contract may carry, the steps around substantial completion, and payment of the retainage once an application is in.

What the rule says

Subsection (a) sets the ceiling as a limit on the contract's own terms: no covered contract may include retainage above 5% of any progress payment [1]. Because the limit is stated per progress payment, each payment is measured on its own. Release runs through a separate application for payment of retainage, which carries a 30-day payment deadline from the date it is submitted [1], and the amount that can still be withheld at that stage is capped as well [1].

How to comply

The section is linked under Sources. Read it with the contract, and with § 5-65-1, which supplies the definition of a contract for construction [2].

What changed recently

Section 37-12-10.1 was added by P.L. 2018, ch. 170, § 3 [1].

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. R.I. Gen. Laws § 37-12-10.1 (retainage limitation; payment of retainage), Rhode Island General Assembly (archived copy, captured 2026-07-24)
  2. R.I. Gen. Laws § 5-65-1, definitions (contract for construction), State of Rhode Island General Assembly (retrieved 2026-10-17)

Changelog

  1. : Page updated.
  2. : 1 more jurisdiction verified and published, 47 of 51 in all.
  3. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  4. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  5. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  6. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  7. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  8. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  9. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  10. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  11. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  12. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  13. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  14. : 10 more jurisdictions verified and published, 46 of 51 in all.
  15. : Page published.
  16. : Dataset first published with 36 of 51 jurisdictions verified.