Retainage · Arkansas

Arkansas retainage law: 5% public cap, 30-day release (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

On an Arkansas public construction contract requiring a performance bond, the agency pays 95% of earned progress payments and retains 5%, holds it in escrow and pays it within 30 days after substantial completion (Ark. Code Ann. § 22-9-604). Materials the contract requires to be stored on site or in a bonded warehouse carry no retainage. Private work has no statewide retainage statute; the contract governs.

Private work

Arkansas · Private workVerified 2026-09-22
Retainage cap
No statewide statute
No statewide statute governs retainage on private construction projects. Arkansas's retainage subchapter (Ark. Code §§ 22-9-601 to 22-9-604) sits in Title 22 'Public Property', Chapter 9 'Public Works', and by its terms applies to 'a construction contract entered into between a public agency and a contractor who is required to furnish a performance bond'.
Deadline
No statewide statute
Statute
No statewide statute

Public work

Arkansas · Public workVerified 2026-09-22
Retainage cap
5%
Ark. Code § 22-9-604(a)(1), as amended by Act 193 of 2009: the contractor is entitled to 95 percent of earned progress payments, with the public agency retaining 5 percent. No retainage may be withheld on the portion of a progress payment covering materials or equipment the contract requires the contractor to purchase and store on the job site or in a bonded warehouse (§ 22-9-604(c)). Applies where the contractor is required to furnish a performance bond.
Deadline
30 days
All sums withheld are held in escrow and must be paid to the contractor within 30 days after the construction contract has been substantially completed. Separately, where the contract allows phased work with completion on partial occupancy, retention must be partially released within 30 days in direct proportion to the value of the completed part of the capital improvement.
What the statute says
In the case of a construction contract entered into between a public agency and a contractor who is required to furnish a performance bond, the contractor shall be entitled to payment of ninety-five percent (95%) of the earned progress payments when due, with the public agency retaining five percent (5%) to assure faithful performance of the contract.
Ark. Code Ann. § 22-9-604, the 5% cap from Act 193 of 2009, § 10; the escrow and 30-day release from Act 471 of 2007, § 3. · Archived copy of the official text, captured 2025-10-12

Who this applies to

Arkansas's retainage statute is written for one kind of job: a construction contract between a public agency and a contractor who has to furnish a performance bond [1]. On those contracts it limits what the agency may hold back from the contractor's earned progress payments and fixes when the money comes back.

Private construction sits outside it. Section 22-9-604 belongs to the Public Works chapter of the Public Property title and speaks to contracts with a public agency [2], and no statewide statute caps retainage or dates its release on a private job. There, the retainage clause the parties signed is the rule, and a lawyer is the person to read it with.

This page covers the agency's side of the ledger. What a prime contractor may withhold from its own subcontractors on the same public job is a question for the subcontract and a lawyer.

What the rule says

Each earned progress payment on a covered contract divides 95/5: the contractor receives 95% when the payment falls due and the agency keeps 5% [1] to assure faithful performance. No retainage comes off the part of a payment that covers materials or equipment the contract requires the contractor to buy and store, whether on the job site or in a bonded warehouse [2]. Everything the agency withholds is held in escrow and goes to the contractor within 30 days [2] after the contract is substantially completed.

How to comply

On a public contract, set the contract documents beside the statute:

On a private contract there is no statute to lay beside the clause. The percentage, any reduction and the payout date are whatever the signed contract says, and a lawyer is the one to read them against Arkansas law.

What changed recently

Act 471 of 2007, § 3, approved March 23, 2007, set out § 22-9-604 with the escrow requirement and the 30-day payout [2]. Act 193 of 2009, § 10, approved February 19, 2009, moved the split from 90%/10% to 95%/5% and deleted the 50%-completion step-down [1].

Related

Retainage laws: other states

Sources

  1. Act 193 of 2009 (SB 302), § 10, amending Ark. Code § 22-9-604(a), Arkansas General Assembly (retrieved 2026-09-22)
  2. Act 471 of 2007 (HB 2585), § 3, setting out Ark. Code § 22-9-604 in full, Arkansas General Assembly (retrieved 2026-09-22)
  3. Act 193 of 2009 (SB 302), § 10, amending Ark. Code § 22-9-604(a), Arkansas General Assembly (archived copy, captured 2025-10-12)
  4. Act 471 of 2007 (HB 2585), § 3, Ark. Code § 22-9-604 escrow and 30-day release, Arkansas General Assembly (archived copy, captured 2025-08-08)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.