Retainage · Connecticut

Connecticut retainage law: 5% private cap, 30-day release (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Connecticut caps private retainage at 5% of a progress payment (Conn. Gen. Stat. § 42-158k), except on HUD projects, residential buildings of up to four units and owner contracts of $25,000 or less; the owner pays it within 30 days of a final-completion certificate or written acceptance. Bonded public work (§ 49-41b) caps it at 7.5% for state agencies (5% after 50% completion), 2.5% for DOT, 5% for municipalities.

Private work

Connecticut · Private workVerified 2026-09-22
Retainage cap
5%
Conn. Gen. Stat. § 42-158k: 'No construction contract may provide for any retainage in an amount that exceeds five per cent of the estimated amount of a progress payment for the life of the construction project.' 'Construction contract' (§ 42-158i(2)) excludes public works or other building contracts with this state, the United States, any other state, or any municipality or political subdivision; projects funded or insured by HUD; owner-contractor contracts of $25,000 or less and subcontracts resulting from them; and contracts for a building intended for residential occupancy containing four or fewer units.
Deadline
30 days
All retainage must be paid by the owner not later than 30 days after issuance of a certificate of final completion by the owner or the owner's authorized representative, or not later than 30 days after the equivalent written acceptance of the construction project work by the owner.
What the statute says
No construction contract may provide for any retainage in an amount that exceeds five per cent of the estimated amount of a progress payment for the life of the construction project.
Conn. Gen. Stat. § 42-158k. · Archived copy of the official text, captured 2025-11-27

Public work

Connecticut · Public workVerified 2026-09-22
Retainage cap
7.5%
Conn. Gen. Stat. § 49-41b applies where a payment bond is required by § 49-41 and the contract requires a performance bond in the full contract price. Three regimes: (1) contracts advertised by the Department of Administrative Services or any other state agency: the awarding authority may not withhold more than 7.5 percent, reduced to 5 percent when 50 percent of the contract is completed, and the prime may not withhold from a subcontractor more than 7.5 percent or the amount withheld from the prime, whichever is less, also reduced to 5 percent at 50 percent completion; (2) contracts advertised by the state Department of Transportation: not more than 2.5 percent, at both tiers; (3) municipal awarding authorities: not more than 5 percent, at both tiers.
Deadline
90 days
Section 49-41b sets the 50 percent-completion reduction and its 90-day payment deadline; it does not itself fix a deadline for final release of the remaining retainage.
What the statute says
the awarding authority shall not withhold more than seven and one-half per cent from any periodic or final payment which is otherwise properly due to the general or prime contractor under the terms of such contract, provided, when fifty per cent of the contract is completed, said amount shall be reduced to five per cent
Conn. Gen. Stat. § 49-41b. · Archived copy of the official text, captured 2026-06-15

Who this applies to

Private work. The limit in § 42-158k reaches every "construction contract" as chapter 742b defines the term [1], including the subcontracts on a covered project. The definition leaves out:

Public work. Section 49-41b governs where § 49-41 requires a payment bond and the contract calls for a performance bond in the full contract price [2]. Its caps bind the awarding authority and, one tier down, the general or prime contractor in what it holds from subcontractors.

What the rule says

Connecticut regulates the private side end to end and the public side by who is paying. A private construction contract may not provide for retainage above 5% [1] of the estimated amount of a progress payment, for the life of the project, and the owner owes all of it within 30 days [1] of certifying final completion or accepting the work in writing. Bonded public work has three caps, set by who awards the contract.

How to comply

Private contracts

Public contracts

The cap turns on who advertised the contract [2]:

On state agency contracts the reduction is payable within 90 days after a complete application for payment showing 50% completion is submitted [2], and the awarding authority must run an early release program for periodic payments from primes to subcontractors. Section 49-41b does not itself fix a deadline for releasing the rest of the retainage [2]; the contract and a lawyer answer that question.

A general contractor or subcontractor that fails to pay as required, after notice by registered or certified mail, owes 1% per month [2] from ten days later, must escrow the claim plus 1% [2] in a Connecticut bank on written demand, and pays the claimant's attorney's fees if it refuses to escrow and the claimant is found to have substantially performed.

What changed recently

P.A. 10-148 cut the private cap from 7.5% to 5% [1], and P.A. 17-182 added the owner-payment provision effective July 1, 2017 [1]. The public section, § 49-41b, dates to P.A. 77-306, and its most recent listed amendment is P.A. 16-104 [2].

Related

Retainage laws: other states

Sources

  1. General Statutes of Connecticut, Chapter 742b, Construction Contracts (§§ 42-158i to 42-158s) (retrieved 2026-09-22)
  2. General Statutes of Connecticut, Chapter 847, Liens (§§ 49-41a, 49-41b, 49-42) (retrieved 2026-09-22)
  3. General Statutes of Connecticut, Chapter 847, Liens (§§ 49-41a, 49-41b, 49-42) (archived copy, captured 2026-06-15)
  4. General Statutes of Connecticut, Chapter 742b, Construction Contracts (§§ 42-158i to 42-158s) (archived copy, captured 2025-11-27)

Changelog

  1. : Page published.
  2. : Dataset first published with 36 of 51 jurisdictions verified.