Who this applies to
Public entities. Section 255.078 limits retainage on any public entity's contract for construction services [1], and § 218.735 applies the same ceiling to local governmental entities [3]. The state-level cap does not reach construction services with a total contract cost of $200,000 or less [1], or work paid for in whole or in part with federal funds subject to contrary federal requirements, and its 2020 amendments do not apply to contracts executed under chapter 337 [1].
Private owners. Section 715.12, the Construction Contract Prompt Payment Law, governs written contracts to improve real property for which part I of chapter 713 authorizes a construction lien, if entered into after December 31, 1992 [4]. It reaches down the chain too: any obligor and obligee may agree to withholding until completion of the entire project [4].
What the rule says
Florida caps the public side and puts the private side on a clock. A public entity may withhold up to 5% [1] of each progress payment, and it may choose to do less (a lower rate, a rate cut in steps under a schedule in the contract, or release of some or all retainage at any point), though none of that is required [1]. A private owner may hold back whatever portion of each progress payment the contract allows until substantial completion of the entire project, but once the triggering events have happened, the whole balance, retainage included, is due within 14 days [4].
How to comply
Public contracts: the punch-list sequence
- The contract has to provide for a list of incomplete items, developed within 30 calendar days [2] after substantial completion; on projects of $10 million [2] or more the contract may allow up to 45 calendar days [2].
- Within 20 business days [2] after the list is developed, and once a proper invoice or payment request is in, the entity pays the rest of the contract balance, retainage included, less 150% [2] of the estimated cost to complete the listed items.
- When the listed items are complete, the contractor may request the amount still held.
- If the entity does not develop the list in time, the contractor may bill for all remaining retainage. Payment is then due within 20 days under § 255.077(9) [2], or within 20 business days under § 218.735(7)(j) [3] when the entity is a local government.
Retainage released to the contractor that is attributable to a subcontractor's or supplier's work has to be passed on to them in a timely way [1].
Private contracts: the payout clock
The 14 days [4] run from any one of these events:
- an architect or engineer certifies substantial completion under the contract, and the contractor substantially completes the items on the owner's written punch list;
- a certificate of occupancy issues, and the punch-list items are completed;
- the owner or its tenant takes possession, and the punch-list items are completed.
If the contract gives no deadline for the owner's punch list, the owner has 15 days [4] from the certificate of substantial completion, the certificate of occupancy or possession, whichever occurs first; with no punch list delivered in time, interest begins 14 days [4] after that first event. On a phased project the rule applies to each phase.
Retainage kept past the deadline accrues interest at the § 55.03 rate plus 12% a year [4], from the date payment was due until it is received, or at the contract rate if that is higher. The right to that interest cannot be waived before payment is due [4]. The contractor may also substitute Treasury or Florida securities, or insured certificates of deposit, for cash retainage [4].
What changed recently
Section 255.078 carries a history of ch. 2005-230, ch. 2020-173 and ch. 2023-134 [1], and § 255.077, which governs closeout and the punch list, lists the same three session laws [2].
Related
- Retainage calculator: the pay-application math behind a Florida progress payment.
- Retainage laws by state: the state index.