Retainage · Louisiana

Louisiana retainage law: 10% or 5% on public works, 45 days (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

La. R.S. 38:2248 limits what a Louisiana public entity may withhold on a public works contract: no more than 10% of the contract price on projects under $500,000, or 5% on projects of $500,000 or more, until 45 days after formal acceptance of the work is recorded or notice of default. The rule cannot be waived and does not cover DOTD contracts. It governs public works only; private work is not addressed by it.

Private work

Louisiana · Private workVerified 2026-09-29
Retainage cap
Not in our verified record
Deadline
Not in our verified record
Statute
Not in our verified record

Public work

Louisiana · Public workVerified 2026-09-29
Retainage cap
10%
La. R.S. 38:2248(A): a public works contract may not let the public entity withhold more than 10% of the contract price on projects under $500,000, or more than 5% on projects of $500,000 or more, until 45 days after recordation of formal acceptance of the work or notice of default. The public entity may not withhold more than the value of the punch list (§ 38:2248(B)(1)). These provisions cannot be waived and do not apply to the Department of Transportation and Development (§ 38:2248(B)(3)).
Deadline
45 days
Expiration of 45 days after recordation of formal acceptance of the work (or notice of default); completed punch-list items are paid when the 45-day lien period expires.
What the statute says
No contracts for the construction, alteration, or repair of any public works executed in conformity with this Part shall provide that the state or any of its agencies, boards, or subdivisions or any other public entity letting such a contract may withhold payment of more than ten percent of the contract price on projects of less than five hundred thousand dollars, and five percent of the contract price on projects of five hundred thousand dollars or more until the expiration of forty-five days after the recordation of formal acceptance of such work, or notice of default by the contractor or subcontractor.
La. R.S. 38:2248. · Archived copy of the official text, captured 2026-04-12

Who this applies to

Section 38:2248 of the Louisiana Revised Statutes governs contracts for the construction, alteration or repair of public works let by the state, its agencies, boards and subdivisions, or any other public entity [1]. Two exclusions shape it: the provisions cannot be waived, and they do not apply to the Department of Transportation and Development [1].

The statute speaks to public works only. Private construction is not addressed by it, so this page covers public work alone; the terms of a private job come from its contract, with a lawyer for anything the contract leaves open.

What the rule says

The limit depends on the size of the project:

The measure is the contract price, not each payment [1]. The withholding may last until 45 days [1] after formal acceptance of the work is recorded, or after notice of default by the contractor or a subcontractor.

A second limit sits alongside the percentage. Under § 38:2248(B)(1), the public entity may not withhold more than the value of the punch list [1]. Punch-list items that have been completed are paid when the 45-day [1] lien period expires.

How to comply

  1. Place the project in its band. Read the contract price against the $500,000 [1] line, then compare the retainage clause with 10% [1] or 5% [1] of that price.
  2. Track recordation. The 45 days [1] run from the recordation of formal acceptance, not from the date the work was finished. The related sections are § 38:2241.1 on substantial completion and § 38:2242(B) on the 45-day period [1].
  3. Price the punch list. Once a punch list exists, the amount withheld is capped at its value [1].
  4. Contract language. A clause that purports to waive these limits does not change them, because § 38:2248 cannot be waived [1].
  5. DOTD work. A Department of Transportation and Development contract is outside this section [1].

This page lays out the statute's terms; it does not settle how they apply to a given contract. That is for the section itself, linked in the Sources below, the contract and a lawyer.

What changed recently

The section traces back to Acts 1954, No. 583, and was last amended by Acts 2020, No. 92 and Acts 2022, No. 756 [1].

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. La. R.S. 38:2248 (withholding payment; punch list), Louisiana State Legislature (archived copy, captured 2026-04-12)

Changelog

  1. : 1 more jurisdiction verified and published, 47 of 51 in all.
  2. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  3. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  4. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  5. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  6. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  7. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  8. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  9. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  10. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  11. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  12. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  13. : Page published.
  14. : 10 more jurisdictions verified and published, 46 of 51 in all.
  15. : Dataset first published with 36 of 51 jurisdictions verified.