Retainage · Indiana

Indiana retainage law: 6% or 3% on public work, 61-day payment (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

On an Indiana local public work contract over $200,000, IC 36-1-12-14 gives the board two choices: withhold no more than 6% of completed work until the job is 50% complete and nothing after, or no more than 3% until substantial completion. State agencies use the same options under IC 5-16-5.5-3.5. Payment is due within 61 days after substantial completion. The statutes cover public work only, not private jobs.

Private work

Indiana · Private workVerified 2026-09-29
Retainage cap
Not in our verified record
Deadline
Not in our verified record
Statute
Not in our verified record

Public work

Indiana · Public workVerified 2026-09-29
Retainage cap
6%
Ind. Code § 36-1-12-14(c): on local public work contracts over $200,000 the board withholds either no more than 6% of the value of work satisfactorily completed until the work is 50% complete and nothing further after that, or no more than 3% until the work is substantially complete. State agencies choose between the same two options under IC 5-16-5.5-3.5. Both were set by P.L. 28-2025 (before that, 10% and 5%). At the contractor's option retainage is held by the board or placed in an escrow account, and the board owes no interest on retainage it holds.
Deadline
61 days
Substantial completion of the public work; an amount equal to 200% of the value of each uncompleted minor item may be held until the item is finished.
What the statute says
To determine the amount of retainage to be withheld, the board shall: (1) withhold no more than six percent (6%) of the dollar value of all work satisfactorily completed until the public work is fifty percent (50%) completed, and nothing further after that; or (2) withhold no more than three percent (3%) of the dollar value of all work satisfactorily completed until the public work is substantially completed.
Ind. Code § 36-1-12-14 (local public work); IC 5-16-5.5-3.5 (state agencies). · Archived copy of the official text, captured 2026-03-13

Who this applies to

Indiana's retainage limits are written for public work. Two sections carry them:

Private construction is not addressed by either section. This page covers public work only; for a private job, the contract and a lawyer supply the answer.

What the rule says

The board chooses between two methods of retainage, each with its own ceiling and its own end point [3].

Under the first option the holdback stops growing at the halfway point. Under the second the ceiling is lower but runs until substantial completion.

Where the money sits is up to the contractor: the board holds it, or it goes into an escrow account [3]. The board owes no interest on retainage it holds itself [3].

After substantial completion, the board or escrow agent pays the contractor within 61 days [3], subject to sections 11 and 12 of the chapter [3]. An amount equal to 200% [3] of the value of each uncompleted minor item may be held back until that item is finished.

How to comply

  1. Find the option in the contract. Look for which of the two methods the retainage clause of a covered public contract uses, then compare its percentage with 6% [3] or 3% [3] accordingly.
  2. Decide where the retainage is held. The escrow option is the contractor's choice [3]. On retainage the board holds itself, the board owes no interest [3].
  3. Date substantial completion. The 61 days [3] run from that date. Keep a list of uncompleted minor items; the holdback for them is capped at 200% [3] of their value.
  4. State agency work. Read the contract against IC 5-16-5.5-3.5, which offers the same 6% or 3% choice [4].

This is a description of the statutes, not a ruling on any contract. The code sections in the Sources below, the contract and a lawyer decide how they apply to a particular project.

What changed recently

The 6% and 3% options took effect on July 1, 2025 [1], under P.L. 28-2025 [4]. They replaced earlier limits of 10% and 5% [2].

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. Indiana State Board of Accounts, 'New Legislation' (2025 Spring Auditors conference), quoting IC 36-1-12-14(c) effective 7-1-25 (retrieved 2026-09-22)
  2. Indiana State Board of Accounts, Township Bulletin, June 2025, new laws (HEA 1033, retainage requirements, amends IC 5-16-5.5-3.5; IC 36-1-12-14) (retrieved 2026-09-22)
  3. Ind. Code § 36-1-12-14, Indiana Code 2025, Title 36, Indiana General Assembly (archived copy, captured 2026-03-13)
  4. Ind. Code § 5-16-5.5-3.5, Indiana Code 2026, Title 5, Indiana General Assembly (archived copy, captured 2026-09-12)

Changelog

  1. : 1 more jurisdiction verified and published, 47 of 51 in all.
  2. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  3. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  4. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  5. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  6. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  7. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  8. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  9. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  10. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  11. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  12. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  13. : Page updated.
  14. : Page published.
  15. : 10 more jurisdictions verified and published, 46 of 51 in all.
  16. : Dataset first published with 36 of 51 jurisdictions verified.