Retainage · Pennsylvania

Pennsylvania retainage law: 10%, then 5%, on public work (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Under 62 Pa.C.S. § 3921, a Pennsylvania government agency may withhold no more than 10% of the amount due until the contract is 50% complete, then returns half of the retainage and holds no more than 5% of the value of completed work (DGS: 6% and 3%). After substantial completion it pays in full within 45 days under § 3941. Title 62 covers public work; private jobs are not addressed by it.

Private work

Pennsylvania · Private workVerified 2026-09-29
Retainage cap
Not in our verified record
Deadline
Not in our verified record
Statute
Not in our verified record

Public work

Pennsylvania · Public workVerified 2026-09-29
Retainage cap
10%
62 Pa.C.S. § 3921(a): a government agency may withhold no more than 10% of the amount due the contractor until the contract is 50% complete; at 50% completion half of the amount retained is returned to the contractor (with architect or engineer approval, satisfactory progress and no specific cause for greater withholding), and afterwards no more than 5% of the value of completed work may be withheld. Where the Department of General Services is the agency, the limits are 6% until 50% satisfactory completion and 3% of the original contract amount after that (§ 3921(b)). Where a prime contractor's claim against the agency rests on increased costs caused by delays or other actions of another prime contractor, additional retainage of one and one-half times the possible liability may be withheld unless the contractor causing the claim furnishes a satisfactory bond. The chapter applies to a contract exceeding $50,000 for construction and excludes Department of Transportation contracts under § 301(c)(1) (§ 3902).
Deadline
45 days
Substantial completion: after final inspection and the architect's or engineer's certificate, the agency pays in full within 45 days, less one and one-half times the cost of any remaining minor items.
What the statute says
A contract may include a provision for the retainage of a portion of the amount due the contractor to insure the proper performance of the contract except that the sum withheld by the government agency from the contractor shall not exceed 10% of the amount due the contractor until 50% of the contract is completed. When the contract is 50% completed, one-half of the amount retained by the government agency shall be returned to the contractor.
62 Pa.C.S. § 3921 (retainage); § 3941 (substantial and final payment). · Archived copy of the official text, captured 2026-07-28

Who this applies to

These rules sit in Title 62 of the Pennsylvania Consolidated Statutes, the procurement title [1]. They govern what a government agency withholds from its contractor on a construction contract exceeding $50,000 [1], and the Department of General Services has a scale of its own [1]. Department of Transportation contracts under 62 Pa.C.S. § 301(c)(1) are outside the chapter's definition of a contract [1]. A related section, § 3922, carries payment down the chain: absent sufficient reason, the contractor pays subcontractors their earned share within 20 days [1] of receiving it.

The statute speaks to public contracts. Private work is not addressed by it, and this page does not cover private jobs; their retainage terms are a matter for the contract and a lawyer.

What the rule says

A contract may provide for retainage to ensure proper performance, within these limits [1]:

  1. Before the halfway point. The agency may withhold no more than 10% [1] of the amount due the contractor until 50% [1] of the contract is completed.
  2. At the halfway point. One-half of the amount retained is returned to the contractor. The return depends on the architect's or engineer's approval, satisfactory progress, and the absence of a specific cause for greater withholding [1].
  3. After the halfway point. The agency may withhold no more than 5% [1] of the value of completed work.

Where the Department of General Services is the agency, the figures are 6% [1] until 50% satisfactory completion and 3% [1] of the original contract amount after that.

A separate allowance covers multi-prime disputes. When a prime contractor's claim against the agency rests on increased costs caused by delays or other actions of another prime contractor, additional retainage of one and one-half times the possible liability may be withheld until the dispute is resolved, unless the contractor causing the claim furnishes a bond satisfactory to the agency [1].

How to comply

The page describes the statute; it does not decide any project. The sections in the Sources below, read with the contract, and a lawyer settle how they apply.

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. 62 Pa.C.S. (Procurement), Title 62 Word version including §§ 3921, 3922 and 3941, Pennsylvania General Assembly (archived copy, captured 2026-07-28)

Changelog

  1. : 1 more jurisdiction verified and published, 47 of 51 in all.
  2. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  3. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  4. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  5. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  6. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  7. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  8. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  9. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  10. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  11. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  12. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  13. : Page updated.
  14. : Page published.
  15. : 10 more jurisdictions verified and published, 46 of 51 in all.
  16. : Dataset first published with 36 of 51 jurisdictions verified.