Retainage · Hawaii

Hawaii retainage law: 5% cap on public contracts (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

On a Hawaii public contract, HRS § 103-32.1 lets the procurement officer withhold no more than 5% of the total amount due the contractor. After 50% of the contract is completed and progress is satisfactory, no additional sum is withheld. A subcontractor that gives its contractor an acceptable bond or collateral can be held to no more than the contractor's own percentage. Private work: the contract governs.

Private work

Hawaii · Private workVerified 2026-09-29
Retainage cap
No statewide statute
No statewide statute governing retainage on private construction projects was located. Hawaii's retainage provisions sit in HRS chapter 103 (Expenditure of Public Money and Public Contracts) and operate through the 'procurement officer' on a 'public contract'.
Deadline
No statewide statute
Statute
No statewide statute

Public work

Hawaii · Public workVerified 2026-09-29
Retainage cap
5%
HRS § 103-32.1(c)(1): the sum withheld by the procurement officer from the contractor shall not exceed five per cent of the total amount due the contractor, and after fifty per cent of the contract is completed and progress is satisfactory no additional sum shall be withheld; if progress is not satisfactory the procurement officer may continue to withhold sums not exceeding five per cent. Retainage does not include sums deducted as liquidated damages (§ 103-32.1(c)(2)). Down the chain: where a subcontractor gives the contractor an acceptable performance and payment bond, other acceptable bond, or other acceptable collateral, the contractor may withhold no more than the same retainage percentage as the contractor's own (§ 103-32.1(d)); absent that, the contractor or subcontractor may negotiate to retain without cause up to ten per cent of each progress payment to a subcontractor (§ 103-32.1(e)(1)), subject to subsection (d). Any retainage is held by the procurement officer (§ 103-32.1(a)).
Deadline
Not in our verified record
What the statute says
The sum withheld by the procurement officer from the contractor shall not exceed five per cent of the total amount due the contractor and that, after fifty per cent of the contract is completed and progress is satisfactory, no additional sum shall be withheld; provided further that if progress is not satisfactory, the procurement officer may continue to withhold, as retainage, sums not exceeding five per cent of the amount due the contractor.
Haw. Rev. Stat. § 103-32.1. · Official text · retrieved 2026-09-29

Who this applies to

Hawaii's retainage rule lives in HRS chapter 103, the chapter on expenditure of public money and public contracts, and it operates through the procurement officer on a public contract [3]. The procurement officer holds whatever retainage is kept [3]. The section also governs what a contractor may keep from its subcontractors on that public job [3].

Private construction has no counterpart: no statewide statute sets a retainage cap or a release date for private work, so the contract governs.

What the rule says

Section 103-32.1(c)(1) caps what the procurement officer withholds from the contractor at 5% [3] of the total amount due. The cap does not stay open for the whole job. Once 50% [3] of the contract is completed and progress is satisfactory, no additional sum is withheld. If progress is not satisfactory, the procurement officer may keep withholding, still within 5% [3] of the amount due. Sums deducted as liquidated damages are not retainage [3].

A tier down, the rule depends on security. Where a subcontractor gives the contractor an acceptable performance and payment bond, another acceptable bond, or other acceptable collateral, the contractor may withhold no more than its own retainage percentage [3]. Without that security, the contractor or subcontractor may negotiate to retain, without cause, up to 10% [3] of each progress payment to a subcontractor, subject to the bonded-subcontractor limit [3].

How to comply

This page reports what the section provides. It does not decide how a particular contract or project is treated; the statute text in the Sources below and a lawyer do that.

What changed recently

Section 103-32.1 was enacted in 1976, L 1976, c 167, and was last amended in 2010, L 2010, c 107, § 1 [3].

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. Haw. Rev. Stat. § 103-32.1 (Contract provision for retainage; subcontractors), Hawaii State Legislature (archived copy, captured 2011-09-30)
  2. Haw. Rev. Stat. § 103-32.2 (Substitution of retainage), Hawaii State Legislature (archived copy, captured 2026-08-23)
  3. Haw. Rev. Stat. § 103-32.1 (Contract provision for retainage; subcontractors), Hawaii State Legislature (retrieved 2026-09-29)
  4. Haw. Rev. Stat. § 103-10.5 (Prompt payment), Hawaii State Legislature (retrieved 2026-09-30)

Changelog

  1. : 1 more jurisdiction verified and published, 47 of 51 in all.
  2. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  3. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  4. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  5. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  6. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  7. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  8. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  9. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  10. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  11. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  12. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  13. : Page updated.
  14. : Page published.
  15. : 10 more jurisdictions verified and published, 46 of 51 in all.
  16. : Dataset first published with 36 of 51 jurisdictions verified.