Retainage · Hawaii

Hawaii retainage law: 5% cap on public contracts (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

On a Hawaii public contract, HRS § 103-32.1 lets the procurement officer withhold no more than 5% of the total amount due the contractor. After 50% of the contract is completed and progress is satisfactory, no additional sum is withheld. A subcontractor that gives its contractor an acceptable bond or collateral can be held to no more than the contractor's own percentage. Private work: the contract governs.

Private work

Hawaii · Private workVerified 2026-09-29
Retainage cap
No statewide statute
No statewide statute governing retainage on private construction projects was located. Hawaii's retainage provisions sit in HRS chapter 103 (Expenditure of Public Money and Public Contracts) and operate through the 'procurement officer' on a 'public contract'.
Deadline
No statewide statute
Statute
No statewide statute

Public work

Hawaii · Public workVerified 2026-09-29
Retainage cap
5%
HRS § 103-32.1(c)(1): the sum withheld by the procurement officer from the contractor shall not exceed five per cent of the total amount due the contractor, and after fifty per cent of the contract is completed and progress is satisfactory no additional sum shall be withheld; if progress is not satisfactory the procurement officer may continue to withhold sums not exceeding five per cent. Retainage does not include sums deducted as liquidated damages (§ 103-32.1(c)(2)). Down the chain: where a subcontractor gives the contractor an acceptable performance and payment bond, other acceptable bond, or other acceptable collateral, the contractor may withhold no more than the same retainage percentage as the contractor's own (§ 103-32.1(d)); absent that, the contractor or subcontractor may negotiate to retain without cause up to ten per cent of each progress payment to a subcontractor (§ 103-32.1(e)(1)), subject to subsection (d). Any retainage is held by the procurement officer (§ 103-32.1(a)).
Deadline
Not in our verified record
What the statute says
The sum withheld by the procurement officer from the contractor shall not exceed five per cent of the total amount due the contractor and that, after fifty per cent of the contract is completed and progress is satisfactory, no additional sum shall be withheld; provided further that if progress is not satisfactory, the procurement officer may continue to withhold, as retainage, sums not exceeding five per cent of the amount due the contractor.
Haw. Rev. Stat. § 103-32.1. · Official text · retrieved 2026-09-29

Who this applies to

Hawaii's retainage rule lives in HRS chapter 103, the chapter on expenditure of public money and public contracts, and it operates through the procurement officer on a public contract [3]. The procurement officer holds whatever retainage is kept [3]. The section also governs what a contractor may keep from its subcontractors on that public job [3].

Private construction has no counterpart: no statewide statute sets a retainage cap or a release date for private work, so the contract governs.

What the rule says

Section 103-32.1(c)(1) caps what the procurement officer withholds from the contractor at 5% [3] of the total amount due. The cap does not stay open for the whole job. Once 50% [3] of the contract is completed and progress is satisfactory, no additional sum is withheld. If progress is not satisfactory, the procurement officer may keep withholding, still within 5% [3] of the amount due. Sums deducted as liquidated damages are not retainage [3].

A tier down, the rule depends on security. Where a subcontractor gives the contractor an acceptable performance and payment bond, another acceptable bond, or other acceptable collateral, the contractor may withhold no more than its own retainage percentage [3]. Without that security, the contractor or subcontractor may negotiate to retain, without cause, up to 10% [3] of each progress payment to a subcontractor, subject to the bonded-subcontractor limit [3].

How to comply

This page reports what the section provides. It does not decide how a particular contract or project is treated; the statute text in the Sources below and a lawyer do that.

What changed recently

Section 103-32.1 was enacted in 1976, L 1976, c 167, and was last amended in 2010, L 2010, c 107, § 1 [3].

Related

Retainage laws: other states

Sources

  1. Haw. Rev. Stat. § 103-32.1 (Contract provision for retainage; subcontractors), Hawaii State Legislature (archived copy, captured 2011-09-30)
  2. Haw. Rev. Stat. § 103-32.2 (Substitution of retainage), Hawaii State Legislature (archived copy, captured 2026-08-23)
  3. Haw. Rev. Stat. § 103-32.1 (Contract provision for retainage; subcontractors), Hawaii State Legislature (retrieved 2026-09-29)
  4. Haw. Rev. Stat. § 103-10.5 (Prompt payment), Hawaii State Legislature (retrieved 2026-09-30)

Changelog

  1. : Page updated.
  2. : Page published.
  3. : 10 more jurisdictions verified and published, 46 of 51 in all.
  4. : Dataset first published with 36 of 51 jurisdictions verified.