Retainage · Illinois

Illinois retainage law: 10% until 50% complete, then 5% (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Illinois uses one 10%-then-5% pattern for private and local public work. On private jobs, 815 ILCS 603/20 allows up to 10% of any payment before the contract is 50% complete, then cuts retainage so no more than 5% is held. On local government public works, 30 ILCS 550/1 sets the same limits for a bonded contractor and down the subcontract chain. A private request to release retainage is paid 15 days after approval.

Private work

Illinois · Private workVerified 2026-09-29
Retainage cap
10%
815 ILCS 603/20 permits retainage of up to 10% of any payment made before the contract is 50% complete; when the contract is 50% complete the retainage already withheld must be reduced so that no more than 5% is held, and no more than 5% of any later payment may be held. Section 20 states no release trigger and no release deadline; the release timing is in 815 ILCS 603/10.
Deadline
A request for release of retainage is a payment application under 815 ILCS 603/5. Under 815 ILCS 603/10(1) the owner pays it within 15 calendar days after approval, and it is deemed approved 25 days after the owner receives it unless the owner provides a written statement of the amount withheld and the reason; under 603/10(2) retainage monies received are passed to a subcontractor whose work has been accepted within 15 calendar days.
What the statute says
Sec. 20. Retainage. No construction contract may permit the withholding of retainage from any payment in excess of the amounts permitted in this Section. A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held.
815 ILCS 603/20 (Contractor Prompt Payment Act). · Archived copy of the official text, captured 2025-05-17

Public work

Illinois · Public workVerified 2026-09-29
Retainage cap
10%
30 ILCS 550/1 (Public Construction Bond Act): before a public works contract is 50% complete, a local governmental unit may not withhold retainage above 10% of any payment to a contractor who furnishes the required bond; at 50% completion it must reduce retainage so that no more than 5% is held, and no more than 5% of later payments may be withheld. Contractors and subcontractors are held to the same 10% and 5% limits toward their subcontractors. From June 1, 2027 (P.A. 104-168) the limits also bind the State, except the Department of Transportation, and a State agency may withhold retainage only when it finds that satisfactory progress has not been achieved. The section sets no release deadline.
Deadline
Not in our verified record
What the statute says
Prior to the completion of 50% of the contract for public works, a local governmental unit may not withhold retainage from any payment to a contractor who furnishes the bond or bond substitute required by this Act in an amount in excess of 10% of any payment made prior to the date of completion of 50% of the contract for public works. When a contract for public works is 50% complete, the local governmental unit shall reduce the retainage so that no more than 5% is held.
30 ILCS 550/1 (Public Construction Bond Act). · Archived copy of the official text, captured 2026-01-06

Who this applies to

Two Illinois statutes carry the same numbers into different settings.

State agency contracts are not yet inside the public limits. That changes on June 1, 2027 [2], as described below.

What the rule says

The rule has two phases, and the dividing line is 50% [1] completion of the contract.

Before that point, retainage may be up to 10% [1] of any payment on a private contract, and no more than 10% [2] of any payment on a local public works contract. When the contract reaches 50% [2] completion, retainage already withheld has to be reduced so that no more than 5% [1] [2] is held. From then on, no more than 5% of any later payment may be withheld [1] [2].

The halfway reduction is not optional under either act. It reaches money already held as well as future pay applications [1] [2].

Neither section sets a trigger or a number of days for releasing the retainage that remains [1] [2]. On private work, the same Act counts a request for release of retainage as a payment application [3]: the owner pays it within 15 calendar days after approval, and it is deemed approved 25 days after the owner receives it unless the owner sends a written statement of the amount withheld and the reason [4].

How to comply

This page describes what the two sections say. Whether they govern a particular contract, and how, is for the statute text in the Sources below, the contract and a lawyer.

What changed recently

The local public works limits were added to 30 ILCS 550/1 by P.A. 103-570, effective January 1, 2024 [2]. P.A. 104-168, effective June 1, 2027 [2], extends them to the State, except the Department of Transportation, and allows a State agency to withhold retainage only when it finds that satisfactory progress has not been achieved [2]. The private section, 815 ILCS 603/20, stands as amended by P.A. 101-432 [1].

Related

Retainage laws: other states

Sources

  1. 815 ILCS 603/20 (Contractor Prompt Payment Act), Illinois General Assembly (archived copy, captured 2025-05-17)
  2. 30 ILCS 550/1 (Public Construction Bond Act), Illinois General Assembly (archived copy, captured 2026-01-06)
  3. 815 ILCS 603/5 (Contractor Prompt Payment Act, definitions), Illinois General Assembly (archived copy, captured 2026-01-17)
  4. 815 ILCS 603/10 (Contractor Prompt Payment Act, construction contracts), Illinois General Assembly (archived copy, captured 2026-01-22)

Changelog

  1. : Page updated.
  2. : Page published.
  3. : 10 more jurisdictions verified and published, 46 of 51 in all.
  4. : Dataset first published with 36 of 51 jurisdictions verified.