Retainage · Illinois

Illinois retainage law: 10% until 50% complete, then 5% (2026)

By Sami Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Illinois uses one 10%-then-5% pattern for private and local public work. On private jobs, 815 ILCS 603/20 allows up to 10% of any payment before the contract is 50% complete, then cuts retainage so no more than 5% is held. On local government public works, 30 ILCS 550/1 sets the same limits for a bonded contractor and down the subcontract chain. A private request to release retainage is paid 15 days after approval.

Private work

Illinois · Private workVerified 2026-09-29
Retainage cap
10%
815 ILCS 603/20 permits retainage of up to 10% of any payment made before the contract is 50% complete; when the contract is 50% complete the retainage already withheld must be reduced so that no more than 5% is held, and no more than 5% of any later payment may be held. Section 20 states no release trigger and no release deadline; the release timing is in 815 ILCS 603/10.
Deadline
A request for release of retainage is a payment application under 815 ILCS 603/5. Under 815 ILCS 603/10(1) the owner pays it within 15 calendar days after approval, and it is deemed approved 25 days after the owner receives it unless the owner provides a written statement of the amount withheld and the reason; under 603/10(2) retainage monies received are passed to a subcontractor whose work has been accepted within 15 calendar days.
What the statute says
Sec. 20. Retainage. No construction contract may permit the withholding of retainage from any payment in excess of the amounts permitted in this Section. A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held.
815 ILCS 603/20 (Contractor Prompt Payment Act). · Archived copy of the official text, captured 2025-05-17

Public work

Illinois · Public workVerified 2026-09-29
Retainage cap
10%
30 ILCS 550/1 (Public Construction Bond Act): before a public works contract is 50% complete, a local governmental unit may not withhold retainage above 10% of any payment to a contractor who furnishes the required bond; at 50% completion it must reduce retainage so that no more than 5% is held, and no more than 5% of later payments may be withheld. Contractors and subcontractors are held to the same 10% and 5% limits toward their subcontractors. From June 1, 2027 (P.A. 104-168) the limits also bind the State, except the Department of Transportation, and a State agency may withhold retainage only when it finds that satisfactory progress has not been achieved. The section sets no release deadline.
Deadline
Not in our verified record
What the statute says
Prior to the completion of 50% of the contract for public works, a local governmental unit may not withhold retainage from any payment to a contractor who furnishes the bond or bond substitute required by this Act in an amount in excess of 10% of any payment made prior to the date of completion of 50% of the contract for public works. When a contract for public works is 50% complete, the local governmental unit shall reduce the retainage so that no more than 5% is held.
30 ILCS 550/1 (Public Construction Bond Act). · Archived copy of the official text, captured 2026-01-06

Who this applies to

Two Illinois statutes carry the same numbers into different settings.

State agency contracts are not yet inside the public limits. That changes on June 1, 2027 [2], as described below.

What the rule says

The rule has two phases, and the dividing line is 50% [1] completion of the contract.

Before that point, retainage may be up to 10% [1] of any payment on a private contract, and no more than 10% [2] of any payment on a local public works contract. When the contract reaches 50% [2] completion, retainage already withheld has to be reduced so that no more than 5% [1] [2] is held. From then on, no more than 5% of any later payment may be withheld [1] [2].

The halfway reduction is not optional under either act. It reaches money already held as well as future pay applications [1] [2].

Neither section sets a trigger or a number of days for releasing the retainage that remains [1] [2]. On private work, the same Act counts a request for release of retainage as a payment application [3]: the owner pays it within 15 calendar days after approval, and it is deemed approved 25 days after the owner receives it unless the owner sends a written statement of the amount withheld and the reason [4].

How to comply

This page describes what the two sections say. Whether they govern a particular contract, and how, is for the statute text in the Sources below, the contract and a lawyer.

What changed recently

The local public works limits were added to 30 ILCS 550/1 by P.A. 103-570, effective January 1, 2024 [2]. P.A. 104-168, effective June 1, 2027 [2], extends them to the State, except the Department of Transportation, and allows a State agency to withhold retainage only when it finds that satisfactory progress has not been achieved [2]. The private section, 815 ILCS 603/20, stands as amended by P.A. 101-432 [1].

Related

How retainage is held on each payment and when it comes back: Retainage in construction. Bill it on the pay application template, which carries retainage on work and on stored materials.

Retainage laws: other states

Sources

  1. 815 ILCS 603/20 (Contractor Prompt Payment Act), Illinois General Assembly (archived copy, captured 2025-05-17)
  2. 30 ILCS 550/1 (Public Construction Bond Act), Illinois General Assembly (archived copy, captured 2026-01-06)
  3. 815 ILCS 603/5 (Contractor Prompt Payment Act, definitions), Illinois General Assembly (archived copy, captured 2026-01-17)
  4. 815 ILCS 603/10 (Contractor Prompt Payment Act, construction contracts), Illinois General Assembly (archived copy, captured 2026-01-22)

Changelog

  1. : 1 more jurisdiction verified and published, 47 of 51 in all.
  2. : California private work corrected: Civ. Code § 8811 (SB 61) caps retention at 5% for contracts entered into on or after January 1, 2026; the row had said no cap.
  3. : Missouri private work corrected: Mo. Rev. Stat. §§ 436.300 to 436.336 cap private retainage at 10% and require release within 30 days of substantial completion; the row had said no private retainage rule.
  4. : Tennessee corrected: Tenn. Code Ann. § 66-34-203 caps owner-to-prime retainage at 5% of the contract, on public and private work; escrow applies to prime contracts of $500,000 or more, and the $300-a-day damages do not apply to public owners.
  5. : Idaho private work added: Idaho Code § 29-115 caps private retention at 5% and requires release within 35 days of final completion; the row had left private work out.
  6. : Rhode Island corrected: the 5% cap in R.I. Gen. Laws § 37-12-10.1 also covers private lienable work of $250,000 or more, and a retainage application may be submitted only 60 days after substantial completion unless the contract allows earlier.
  7. : Oklahoma public work corrected: since November 1, 2022, 61 O.S. §§ 113.1 and 226 reduce retainage to 2.5% of the amount earned to date after 50% completion with satisfactory progress, with no bond condition.
  8. : Montana public work corrected: state and local public contracts are capped at 5% under Mont. Code Ann. § 18-2-316, and final payment on building contracts is due within 30 days of final acceptance (§ 18-2-306).
  9. : Delaware public work corrected: 29 Del. C. § 6516(f)(3) requires retainage to be paid within 60 days after completion or notice of completion, with interest available from the 61st day; the row had no release deadline.
  10. : District of Columbia corrected: D.C. Code § 2-203.01 requires a 10% retent on District construction contracts until completion and acceptance, and the Private Contractor and Subcontractor Prompt Payment Act counts retainage as an undisputed amount due on its schedule; both rows had said no statute.
  11. : Colorado private work updated: HB26-1311 lets a contractor or subcontractor tender a retainage bond of up to 5% in lieu of retainage on contracts from August 12, 2026, and the owner must accept a compliant bond.
  12. : Kentucky private work updated: 2025 Ky. Acts ch. 156 raised the KRS 371.160 escrow threshold to $2,000,000 and barred waiving it by contract.
  13. : Page updated.
  14. : Page published.
  15. : 10 more jurisdictions verified and published, 46 of 51 in all.
  16. : Dataset first published with 36 of 51 jurisdictions verified.