Lien deadlines · Maryland

Maryland mechanics lien deadlines: notice, lien and suit (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Under Md. Code, Real Prop. §§ 9-101 to 9-114, the lien filing deadline for direct contractors, subcontractors, sub-subcontractors, suppliers and laborers is 180 days after the work has been finished or the materials furnished (§ 9-105(a)), and the deadline to sue is 1 year after the petition to establish the lien is first filed (§ 9-109).

Maryland · Lien deadlinesVerified 2026-10-02
Lien filing
180 days after the work has been finished or the materials furnished
Preliminary notice
Subcontractor, Sub-subcontractor, Supplier, Laborer: 120 days after doing the work or furnishing the materials; Direct contractor: None required
Deadline to sue
1 year after the petition to establish the lien is first filed

Preliminary notice

WhoProject typeBranchDeadlineStatute
Subcontractor, Sub-subcontractor, Supplier, LaborerAnyDefault120 days after doing the work or furnishing the materialsStatute: Md. Code, Real Prop. § 9-104(a)(1); Md. Code, Real Prop. § 9-104(a)(2); Md. Code, Real Prop. § 9-101(g); Md. Code, Real Prop. § 9-104(c); Md. Code, Real Prop. § 9-104(d); Md. Code, Real Prop. § 9-104(e)
What the statute says about it. A subcontractor has no lien under this subtitle unless it gives this notice within that time. Recipients: The owner, or any of the owners if there is more than one. Delivery: Registered or certified mail, return receipt requested, or personal delivery to the owner by the claimant or his agent. If notice cannot be given on account of absence or other causes, it may be placed on the door or other front part of the building within 120 days, in the presence of a competent witness.
Direct contractorAnyDefaultNone requiredStatute: Md. Code, Real Prop. § 9-104(a)(1); Md. Code, Real Prop. § 9-101(d); Md. Code, Real Prop. § 9-101(g)
(a) (1) A subcontractor doing work or furnishing materials or both for or about a building other than a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle unless, within 120 days after doing the work or furnishing the materials, the subcontractor gives written notice of an intention to claim a lien substantially in the form specified in subsection (b) of this section.
Md. Code, Real Prop. § 9-104(a)(1) · Official text · retrieved 2026-10-02
(2) A subcontractor doing work or furnishing materials or both for or about a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle unless, within 120 days after doing work or furnishing materials for or about that single family dwelling, the subcontractor gives written notice of an intention to claim a lien in accordance with subsection (a)(1) of this section and the owner has not made full payment to the contractor prior to receiving the notice.
Md. Code, Real Prop. § 9-104(a)(2) · Official text · retrieved 2026-10-02
(g) “Subcontractor” means a person who has a contract with anyone except the owner or his agent.
Md. Code, Real Prop. § 9-101(g) · Official text · retrieved 2026-10-02
(c) The notice is effective if given by registered or certified mail, return receipt requested, or personally delivered to the owner by the claimant or his agent.
Md. Code, Real Prop. § 9-104(c) · Official text · retrieved 2026-10-02
(d) If there is more than one owner, the subcontractor may comply with this section by giving the notice to any of the owners.
Md. Code, Real Prop. § 9-104(d) · Official text · retrieved 2026-10-02
(e) If notice cannot be given on account of absence or other causes, the subcontractor, or his agent, in the presence of a competent witness and within 120 days, may place the notice on the door or other front part of the building.
Md. Code, Real Prop. § 9-104(e) · Official text · retrieved 2026-10-02
(d) “Contractor” means a person who has a contract with an owner.
Md. Code, Real Prop. § 9-101(d) · Official text · retrieved 2026-10-02

Lien filing

WhoProject typeBranchDeadlineStatute
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyDefault180 days after the work has been finished or the materials furnishedStatute: Md. Code, Real Prop. § 9-105(a)
(a) In order to establish a lien under this subtitle, a person entitled to a lien shall file proceedings in the circuit court for the county where the land or any part of the land is located within 180 days after the work has been finished or the materials furnished.
Md. Code, Real Prop. § 9-105(a) · Official text · retrieved 2026-10-02

Deadline to sue

WhoProject typeBranchDeadlineStatute
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyDefault1 year after the petition to establish the lien is first filedStatute: Md. Code, Real Prop. § 9-109
What the statute says about it. If a petition to enforce the lien is filed within the one-year period, the lien remains in full force until the enforcement proceedings conclude, and after that only in accordance with the decree.
The right to enforce any lien established under this subtitle expires at the end of one year from the day on which the petition to establish the lien was first filed.
Md. Code, Real Prop. § 9-109 · Official text · retrieved 2026-10-02
If such petition is filed within the one-year period, the right to a lien or the lien, or any bond given to obtain a release of lien, shall remain in full force and effect until the conclusion of the enforcement proceedings and thereafter only in accordance with the decree entered in the case.
Md. Code, Real Prop. § 9-109 · Official text · retrieved 2026-10-02

Residential projects

For a single family dwelling being erected on the owner’s land for the owner’s own residence, a subcontractor has no lien unless it gives the notice within 120 days and the owner has not made full payment to the contractor before receiving the notice, and the lien cannot exceed what the owner owes under the contract when the notice is given.

(2) A subcontractor doing work or furnishing materials or both for or about a single family dwelling being erected on the owner’s land for his own residence is not entitled to a lien under this subtitle unless, within 120 days after doing work or furnishing materials for or about that single family dwelling, the subcontractor gives written notice of an intention to claim a lien in accordance with subsection (a)(1) of this section and the owner has not made full payment to the contractor prior to receiving the notice.
Md. Code, Real Prop. § 9-104(a)(2) · Official text · retrieved 2026-10-02
(3) Notwithstanding any other provision of this section to the contrary, the lien of the subcontractor against a single family dwelling being erected on the land of the owner for his own residence shall not exceed the amount by which the owner is indebted under the contract at the time the notice is given.
Md. Code, Real Prop. § 9-104(f)(3) · Official text · retrieved 2026-10-02

How the days are counted

The day of the event is not counted, and the last day of the period is.

(a) In computing a period of time described in a statute, the day of the act, event, or default after which the designated period of time begins to run may not be included.
Md. Code, Gen. Prov. § 1-302(a) · Official text · retrieved 2026-10-02

A last day that falls on a Sunday or a legal holiday moves to the next day that is not one.

(b) The last day of the period of time computed under subsection (a) of this section shall be included unless: (1) it is a Sunday or legal holiday, in which case the period runs until the end of the next day that is not a Sunday or legal holiday; or (2) the act to be done is the filing of a paper in court and the office of the clerk of the court is not open on the last day of the period of time, or is closed for a part of a day, in which case the period runs until the end of the next day that is not a Saturday, Sunday, legal holiday, or day on which the office is not open the entire day during ordinary business hours.
Md. Code, Gen. Prov. § 1-302(b) · Official text · retrieved 2026-10-02

A last day when the act to be done is the filing of a paper in court and the office of the clerk of the court is not open on that day, or is closed for a part of it also moves.

Who the deadlines apply to

Maryland sets its mechanics lien timetable in Md. Code, Real Prop. §§ 9-101 to 9-114. Two of its stages, the lien filing and the deadline to sue, are each a single rule listed for direct contractors, subcontractors, sub-subcontractors, suppliers and laborers on any project type [3] [4].

The notice stage is split by role. Section 9-101(g) defines a subcontractor as anyone with a contract with someone other than the owner or the owner's agent [2]. The notice rule names subcontractors, sub-subcontractors, suppliers and laborers [1]. For the direct contractor, the same stage reads None required [1].

How the periods run

Notice of an intention to claim a lien. Section 9-104 calls its notice a written notice of an intention to claim a lien, and the page lists it as the preliminary notice. Its period is 120 days after doing the work or furnishing the materials [1]. For a building other than a single family dwelling being erected on the owner's land for the owner's own residence, § 9-104(a)(1) states that a subcontractor has no lien under this subtitle unless it gives this notice within that time [1]. The rows under the table name who receives it and the ways it may be delivered.

Establishing the lien. In Maryland the lien filing stage is a court step. A person claiming a lien files proceedings in the circuit court to establish it, and § 9-105(a) sets the period at 180 days after the work has been finished or the materials furnished [3].

Enforcement. The last clock starts with a court filing too. Section 9-109 sets the time to enforce an established lien at 1 year after the petition to establish the lien is first filed [4]. The same section also states that if a petition to enforce the lien is filed within the one-year period, the lien stays in full force until the enforcement proceedings conclude, and after that only in accordance with the decree [4]. The calculator counts this date from the date entered for the first filing of the petition to establish the lien.

How residential work is treated

Every rule on this page is listed for any project type. Section 9-104 adds one set of terms for a single family dwelling being erected on the owner's land for the owner's own residence [1]. For that dwelling, a subcontractor has no lien unless two things are true: it gives the notice within the period § 9-104(a)(2) sets, and the owner has not made full payment to the contractor before receiving the notice [1]. Under § 9-104(f)(3), the subcontractor's lien against that dwelling cannot exceed what the owner owes under the contract when the notice is given [1].

Counting the days

Md. Code, Gen. Prov. § 1-302(a) leaves out the day of the act or event that starts a period, and § 1-302(b) includes the last day [5]. A last day that is a Sunday or a legal holiday is not counted, and the period runs to the end of the next day that is neither; this moving rule reaches every stage on this page [5].

A second clause covers filings in court. When the act is the filing of a paper in court and the clerk's office is not open on the last day, or is closed for part of it, the period runs to the end of the next day that is not a Saturday, Sunday or legal holiday and on which that office is open the entire day during ordinary business hours [5].

Section 1-111(a) defines a legal holiday for the Code [6]. Unless the Code expressly provides otherwise, § 1-111(b) observes a legal holiday on its listed date, or on the next Monday when that date falls on a Sunday [6].

Related

Lien deadlines: other states

Sources

  1. Md. Code, Real Prop. § 9-104, Maryland General Assembly (retrieved 2026-10-02)
  2. Md. Code, Real Prop. § 9-101, Maryland General Assembly (retrieved 2026-10-02)
  3. Md. Code, Real Prop. § 9-105, Maryland General Assembly (retrieved 2026-10-02)
  4. Md. Code, Real Prop. § 9-109, Maryland General Assembly (retrieved 2026-10-02)
  5. Md. Code, Gen. Prov. § 1-302, Maryland General Assembly (retrieved 2026-10-02)
  6. Md. Code, Gen. Prov. § 1-111, Maryland General Assembly (retrieved 2026-10-02)

Changelog

  1. : Page published.
  2. : 10 more jurisdictions published: Alabama, Alaska, Arkansas, Colorado, Connecticut, Delaware, District of Columbia, Hawaii, Idaho and Indiana.
  3. : 10 more jurisdictions published: Iowa, Kansas, Louisiana, Maine, Maryland, Massachusetts, Michigan, Minnesota, Mississippi and Missouri.
  4. : Dataset first published: 9 of 51 jurisdictions published.