Lien deadlines · Massachusetts

Massachusetts mechanics lien deadlines: notice, lien and suit (2026)

By Oussama Chicha, EditorUpdated Checked against primary sources · not yet reviewed by a licensed professionalFact-checked
Quick answer

Massachusetts' direct contractor lien filing deadline is the earliest of 60 days after a notice of substantial completion is filed or recorded, ninety days after filing or recording of the notice of termination under section two B, and 90 days after such person or any person by, through or under him last performed or furnished labor or materials or both labor and materials (Mass. Gen. Laws ch. 254, § 2). Suit: § 11.

Massachusetts · Lien deadlinesVerified 2026-10-02
Lien filing
the earlier of 60 days after a notice of substantial completion is filed or recorded and 90 days after such person or any person by, through or under him last performed or furnished labor or materials or both labor and materials
Direct contractor
Preliminary notice
None required
Deadline to sue
90 days after the statement required by section eight is filed

Preliminary notice

WhoProject typeBranchDeadlineStatute
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyDefaultNone requiredStatute: Mass. Gen. Laws ch. 254, § 2; Mass. Gen. Laws ch. 254, § 4; Mass. Gen. Laws ch. 254, § 1
What the statute says about it. Section 4 provides an optional notice of identification. A claimant with no direct contractual relationship with the original contractor that has not given one by certified mail, return receipt requested, within thirty days of commencing its performance has a lien no greater than the amount due or to become due under the subcontract between the original contractor and the subcontractor whose work includes its work, as of the date it files its notice of contract. This limit does not apply to liens for labor by persons defined in section 1.
A person entering into a written contract with the owner of any interest in real property, or with any person acting for, on behalf of, or with the consent of such owner for the whole or part of the erection, alteration, repair or removal of a building, structure, or other improvement to real property, or for furnishing material or rental equipment, appliances, or tools therefor, shall have a lien upon such real property, land, building, structure or improvement owned by the party with whom or on behalf of whom the contract was entered into, as appears of record on the date when notice of said contract is filed or recorded in the registry of deeds for the county or district where such land lies, to secure the payment of all labor, including construction management and general contractor services, and material or rental equipment, appliances, or tools which shall be furnished by virtue of said contract.
Mass. Gen. Laws ch. 254, § 2 · Archived copy of the official text, captured 2026-03-05
Upon filing or recording a notice, as hereinbefore provided, and giving actual notice to the owner of such filing, the subcontractor shall have a lien upon such real property, land, building, structure or improvement owned by the party who entered into the original contract as appears of record at the time of such filing, to secure the payment of all labor and material and rental equipment, appliances or tools or professional services which he is to furnish or has furnished for the building or structure or other improvement, regardless of the amount stated in the notice of contract.
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08
A person to whom a debt is due for personal labor performed in the erection, alteration, repair or removal of a building or structure upon land or improvement or alteration to real property, by virtue of an agreement with, or by consent of, the owner of such building or structure, or of a person having authority from or rightfully acting for such owner in procuring or furnishing such labor, shall, under the provisions of this chapter, other than section four, have a lien upon such building or structure and upon such interest in such real property, land, building, structure, or improvement owned by the party authorizing or consenting to said work, for not more than thirty days' work actually performed for the ninety days next prior to his filing a statement as provided in section eight.
Mass. Gen. Laws ch. 254, § 1 · Archived copy of the official text, captured 2025-11-12
If the person claiming a lien under this section has no direct contractual relationship with the original contractor, except for liens for labor by persons defined in section one of this chapter, the amount of such lien shall not exceed the amount due or to become due under the subcontract between the original contractor and the subcontractor whose work includes the work of the person claiming the lien as of the date such person files his notice of contract, unless the person claiming such lien has, within thirty days of commencement of his performance, given written notice of identification by certified mail return receipt requested to the original contractor in substantially the following form:
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08

Lien filing

WhoProject typeBranchDeadlineStatute
Direct contractorAnyDefaultthe earlier of 60 days after a notice of substantial completion is filed or recorded and 90 days after such person or any person by, through or under him last performed or furnished labor or materials or both labor and materialsStatute: Mass. Gen. Laws ch. 254, § 2
Subcontractor, Sub-subcontractor, SupplierAnyDefaultthe earlier of 60 days after a notice of substantial completion is filed or recorded and 90 days after the last day a person who may enforce a lien under section two, or anyone claiming by, through or under him, performed or furnished labor or materials or both labor and materials to the project or furnished rental equipment, appliances or tools, or performed professional servicesStatute: Mass. Gen. Laws ch. 254, § 4
Direct contractor, Subcontractor, Sub-subcontractor, SupplierAnyDefaultthe earlier of 90 days after a notice of substantial completion is filed or recorded and 120 days after the last day a person who may enforce a lien under section two, or anyone claiming by, through or under him, performed or furnished labor or material or both labor and materials or furnished rental equipment, appliances or toolsStatute: Mass. Gen. Laws ch. 254, § 8
What the statute says about it. If the statement is not filed or recorded within that time, the lien under section 2 or 4 is dissolved.
LaborerAnyFor a lien under section 1 for personal labor performed by virtue of an agreement with, or by consent of, the owner or a person having authority from or rightfully acting for the ownerA statement filed or recorded within the ninety days provided in section 1, for not more than thirty days of work actually performed in the ninety days before it is filedStatute: Mass. Gen. Laws ch. 254, § 1; Mass. Gen. Laws ch. 254, § 8
What the statute says about it. If the statement is not filed or recorded within the ninety days provided in section 1, the lien under section 1 is dissolved.
LaborerAnyFor a person who furnishes labor under a written contract with a contractor, or with a subcontractor of such contractor, and files a notice of contract under section 4the earlier of 60 days after a notice of substantial completion is filed or recorded and 90 days after the last day a person who may enforce a lien under section two, or anyone claiming by, through or under him, performed or furnished labor or materials or both labor and materials to the project or furnished rental equipment, appliances or tools, or performed professional servicesStatute: Mass. Gen. Laws ch. 254, § 4
LaborerAnyFor a person who furnishes labor under a written contract with a contractor, or with a subcontractor of such contractor, and has a lien under section 4the earlier of 90 days after a notice of substantial completion is filed or recorded and 120 days after the last day a person who may enforce a lien under section two, or anyone claiming by, through or under him, performed or furnished labor or material or both labor and materials or furnished rental equipment, appliances or toolsStatute: Mass. Gen. Laws ch. 254, § 4; Mass. Gen. Laws ch. 254, § 8
What the statute says about it. If the statement is not filed or recorded within that time, the lien under section 4 is dissolved.
A person entering into a written contract with the owner of any interest in real property, or with any person acting for, on behalf of, or with the consent of such owner for the whole or part of the erection, alteration, repair or removal of a building, structure, or other improvement to real property, or for furnishing material or rental equipment, appliances, or tools therefor, shall have a lien upon such real property, land, building, structure or improvement owned by the party with whom or on behalf of whom the contract was entered into, as appears of record on the date when notice of said contract is filed or recorded in the registry of deeds for the county or district where such land lies, to secure the payment of all labor, including construction management and general contractor services, and material or rental equipment, appliances, or tools which shall be furnished by virtue of said contract.
Mass. Gen. Laws ch. 254, § 2 · Archived copy of the official text, captured 2026-03-05
Such person may file or record the notice of contract at any time after execution of the written contract whether or not the date for performance stated in such written contract has passed and whether or not the work under such written contract has been performed, but not later than the earliest of: (i) sixty days after filing or recording of the notice of substantial completion under section two A; or (ii) ninety days after filing or recording of the notice of termination under section two B; or (iii) ninety days after such person or any person by, through or under him last performed or furnished labor or materials or both labor and materials.
Mass. Gen. Laws ch. 254, § 2 · Archived copy of the official text, captured 2026-03-05
Whoever furnishes labor, including subcontractor construction management services, or who furnishes material, or both labor and material, or furnishes rental equipment, appliances or tools, or who performs professional services, under a written contract with a contractor, or with a subcontractor of such contractor, may file or record in the registry of deeds for the county or district where such land lies a notice of his contract substantially in the following form:
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08
Such person may file or record the notice of contract at any time after execution of the written contract whether or not the date for performance stated in such written contract has passed and whether or not the work under such contract has been performed, but not later than the earliest of: (i) sixty days after filing or recording the notice of substantial completion under section two A; or (ii) ninety days after filing or recording of the notice of termination under section two B; or (iii) ninety days after the last day a person entitled to enforce a lien under section two or anyone claiming by, through or under him performed or furnished labor or materials or both labor and materials to the project or furnished rental equipment, appliances or tools, or performed professional services.
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08
Upon filing or recording a notice, as hereinbefore provided, and giving actual notice to the owner of such filing, the subcontractor shall have a lien upon such real property, land, building, structure or improvement owned by the party who entered into the original contract as appears of record at the time of such filing, to secure the payment of all labor and material and rental equipment, appliances or tools or professional services which he is to furnish or has furnished for the building or structure or other improvement, regardless of the amount stated in the notice of contract.
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08
Liens under sections two and four shall be dissolved unless the contractor, subcontractor, or some person claiming by, through or under them, shall, not later than the earliest of: (i) ninety days after the filing or recording of the notice of substantial completion under section two A; (ii) one hundred and twenty days after the filing or recording of the notice of termination under section two B; or (iii) one hundred and twenty days after the last day a person, entitled to enforce a lien under section two or anyone claiming by, through or under him, performed or furnished labor or material or both labor and materials or furnished rental equipment, appliances or tools, file or record in the registry of deeds in the county or district where the land lies a statement, giving a just and true account of the amount due or to become due him, with all just credits, a brief description of the property, and the names of the owners set forth in the notice of contract.
Mass. Gen. Laws ch. 254, § 8 · Archived copy of the official text, captured 2026-05-12
A person to whom a debt is due for personal labor performed in the erection, alteration, repair or removal of a building or structure upon land or improvement or alteration to real property, by virtue of an agreement with, or by consent of, the owner of such building or structure, or of a person having authority from or rightfully acting for such owner in procuring or furnishing such labor, shall, under the provisions of this chapter, other than section four, have a lien upon such building or structure and upon such interest in such real property, land, building, structure, or improvement owned by the party authorizing or consenting to said work, for not more than thirty days' work actually performed for the ninety days next prior to his filing a statement as provided in section eight.
Mass. Gen. Laws ch. 254, § 1 · Archived copy of the official text, captured 2025-11-12
A lien under section one shall be dissolved unless a like statement, giving the names of the owner of record at the time the work was performed or at the time of filing the statement, is filed or recorded in the appropriate registry of deeds within the ninety days provided in said section.
Mass. Gen. Laws ch. 254, § 8 · Archived copy of the official text, captured 2026-05-12
Such notice may also be filed by a person or his assignee, agent, authorized representative or third party beneficiary to whom amounts are due or for whose benefit amounts are computed and due for or on the basis of the labor of that person performing labor under a written contract with a contractor, or with a subcontractor of such contractor and the person filing such notice shall not be required to itemize the amount of the contract, the amount of pending changes in the contract, the amount of outstanding claims or the amount paid in such notice.
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08

Service of the lien

WhoProject typeBranchDeadlineStatute
Subcontractor, Sub-subcontractor, SupplierAnyDefaultActual notice to the owner of the filing or recording of the notice of contract, with no period statedStatute: Mass. Gen. Laws ch. 254, § 4
What the statute says about it. The subcontractor has its lien upon filing or recording the notice of contract and giving the owner actual notice of that filing. Recipients: The owner.
LaborerAnyFor a person who furnishes labor under a written contract with a contractor, or with a subcontractor of such contractor, and files a notice of contract under section 4Actual notice to the owner of the filing or recording of the notice of contract, with no period statedStatute: Mass. Gen. Laws ch. 254, § 4
What the statute says about it. The person has its lien under section 4 upon filing or recording the notice of contract and giving the owner actual notice of that filing. Recipients: The owner.
Upon filing or recording a notice, as hereinbefore provided, and giving actual notice to the owner of such filing, the subcontractor shall have a lien upon such real property, land, building, structure or improvement owned by the party who entered into the original contract as appears of record at the time of such filing, to secure the payment of all labor and material and rental equipment, appliances or tools or professional services which he is to furnish or has furnished for the building or structure or other improvement, regardless of the amount stated in the notice of contract.
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08
Whoever furnishes labor, including subcontractor construction management services, or who furnishes material, or both labor and material, or furnishes rental equipment, appliances or tools, or who performs professional services, under a written contract with a contractor, or with a subcontractor of such contractor, may file or record in the registry of deeds for the county or district where such land lies a notice of his contract substantially in the following form:
Mass. Gen. Laws ch. 254, § 4 · Archived copy of the official text, captured 2026-05-08

Deadline to sue

WhoProject typeBranchDeadlineStatute
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyDefault90 days after the statement required by section eight is filedStatute: Mass. Gen. Laws ch. 254, § 11
What the statute says about it. If no civil action to enforce the lien is commenced within that time, the lien is dissolved.
Direct contractor, Subcontractor, Sub-subcontractor, Supplier, LaborerAnyOnce a civil action to enforce the lien is commencedAn attested copy of the complaint filed in the registry of deeds within thirty days of the commencement of the actionStatute: Mass. Gen. Laws ch. 254, § 5
What the statute says about it. If the attested copy is not filed and recorded within that time, the lien is dissolved.
The lien shall be dissolved unless a civil action to enforce it is commenced within ninety days after the filing of the statement required by section eight.
Mass. Gen. Laws ch. 254, § 11 · Archived copy of the official text, captured 2026-05-19
An attested copy of the complaint, which shall contain a brief description of the property sufficient to identify it, and a statement of the amount due, shall be filed in the registry of deeds and recorded as provided in section nine within thirty days of the commencement of the action, or such lien shall be dissolved.
Mass. Gen. Laws ch. 254, § 5 · Archived copy of the official text, captured 2025-12-11

Notice of commencement and completion

Upon or after substantial completion, meaning the work under the written contract is sufficiently complete to be occupied or used for its intended use, the owner and contractor file or record a notice of substantial completion in the registry of deeds. The owner mails a copy by certified mail to every person who filed a notice of contract under section 4, and the contractor to every person with a written contract directly with it and every person who gave it a notice of identification.

''Substantial completion'', that work under the written contract is sufficiently complete so that it can be occupied or utilized for its intended use.
Mass. Gen. Laws ch. 254, § 2A · Archived copy of the official text, captured 2026-06-05
Upon or after substantial completion of any contract subject to the provisions of section two, the owner and contractor shall execute and file or record in the appropriate registry of deeds a notice of substantial completion in substantially the following form:
Mass. Gen. Laws ch. 254, § 2A · Archived copy of the official text, captured 2026-06-05
A copy of such notice, indicating the date of filing or recording, shall be mailed by certified mail return receipt requested by the owner to every person who has filed a notice of contract under section four and by the contractor to every person who has entered into a written contract directly with the contractor and every person who has given written notice of identification to the contractor claiming by, through, or under him as provided in section four.
Mass. Gen. Laws ch. 254, § 2A · Archived copy of the official text, captured 2026-06-05

If the contract is terminated before a notice of substantial completion is filed or recorded and its copies delivered, the owner files or records a notice of termination in the registry of deeds.

If, prior to the filing or recording in the registry of deeds and delivery of the copies of the notice of substantial completion described in section two A, any contract subject to the provisions of section two shall have been terminated, the owner shall execute and file or record in the appropriate registry of deeds a notice of termination in substantially the following form:
Mass. Gen. Laws ch. 254, § 2B · Archived copy of the official text, captured 2026-03-11

How the days are counted

A last day that falls on a Sunday or a legal holiday moves to the next business day.

Except as otherwise provided, when the day or the last day for the performance of any act, including the making of any payment or tender of payment, authorized or required by statute or by contract, falls on Sunday or a legal holiday, the act may, unless it is specifically authorized or required to be performed on Sunday or on a legal holiday, be performed on the next succeeding business day.
Mass. Gen. Laws ch. 4, § 9 · Archived copy of the official text, captured 2026-01-15

Who the deadlines apply to

Under Mass. Gen. Laws ch. 254, the section 2 notice of contract rule names the direct contractor, a person with a written contract with the owner or with a person acting for, on behalf of, or with the consent of the owner [1]. The section 4 rule names subcontractors, sub-subcontractors and suppliers [2], and the section 8 statement rule names all four roles [4]. Laborers appear at the filing stage only in rules with a condition. The suit rules name all five roles, and no rule is limited by project type.

The preliminary notice stage reads None required [2]. Section 4 describes an optional notice of identification to the original contractor. For a claimant with no direct contractual relationship with the original contractor that gives none within thirty days [2] of commencing performance, section 4 limits the amount of the lien, except for liens for labor by persons defined in section 1.

How the periods run

Notice of contract. For the direct contractor, the section 2 rule reads the earlier of 60 days after a notice of substantial completion is filed or recorded and 90 days after such person or any person by, through or under him last performed or furnished labor or materials or both labor and materials [1]. Section 2 also counts "ninety days after filing or recording of the notice of termination under section two B", and the deadline is the earliest of the three [1]. The section 4 rule runs from the same three events [2]. Under section 4, the subcontractor has its lien upon filing or recording the notice and giving "actual notice to the owner" of that filing [2]. No period is stated for that notice.

Statement of the amount due. The section 8 statement counts from the same three events. If the statement is not filed or recorded within that time, the lien under section 2 or 4 is dissolved [4].

Laborers. For a lien under section 1 for personal labor performed by virtue of an agreement with, or by consent of, the owner or a person having authority from or rightfully acting for the owner, the rule reads: A statement filed or recorded within the ninety days provided in section 1, for not more than thirty days of work actually performed in the ninety days before it is filed [3] [4]. It counts back from the statement's own filing, so no date is counted. Missing it dissolves the section 1 lien [4].

For a person who furnishes labor under a written contract with a contractor, or with a subcontractor of such contractor, three further rules apply: one for a person who files a notice of contract under section 4, matching the subcontractor rule [2], one for the actual notice to the owner of that filing, with no period stated [2], and one for a person who has a lien under section 4, matching the section 8 statement rule [4].

Suit. The deadline to sue is 90 days after the statement required by section eight is filed [5]; without a civil action commenced within that time, the lien is dissolved. Once a civil action to enforce the lien is commenced, section 5 adds: An attested copy of the complaint filed in the registry of deeds within thirty days of the commencement of the action [6], or the lien is dissolved.

Notices of substantial completion and termination

Section 2A treats substantial completion as work under the written contract sufficiently complete to be occupied or used for its intended use. Upon or after that point, the owner and contractor file or record a notice of substantial completion in the registry of deeds. Section 2A also directs certified mail copies from the owner and from the contractor [7].

If the contract is terminated before that notice is filed or recorded and its copies delivered, the owner files or records a notice of termination [8]. Sections 2, 4 and 8 also count their periods from that notice [1] [2] [4].

Counting the days

Under Mass. Gen. Laws ch. 4, § 9, when the day or the last day for an act falls on a Sunday or a legal holiday, the act may be performed on the next succeeding business day [9]. Section 9 does not name Saturdays. Clause Eighteenth of ch. 4, § 7 lists legal holidays [10].

Related

Lien deadlines: other states

Sources

  1. Mass. Gen. Laws ch. 254, § 2, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-03-05)
  2. Mass. Gen. Laws ch. 254, § 4, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-05-08)
  3. Mass. Gen. Laws ch. 254, § 1, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2025-11-12)
  4. Mass. Gen. Laws ch. 254, § 8, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-05-12)
  5. Mass. Gen. Laws ch. 254, § 11, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-05-19)
  6. Mass. Gen. Laws ch. 254, § 5, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2025-12-11)
  7. Mass. Gen. Laws ch. 254, § 2A, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-06-05)
  8. Mass. Gen. Laws ch. 254, § 2B, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-03-11)
  9. Mass. Gen. Laws ch. 4, § 9, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-01-15)
  10. Mass. Gen. Laws ch. 4, § 7, The General Court of the Commonwealth of Massachusetts (archived copy, captured 2026-09-23)

Changelog

  1. : Page published.
  2. : 10 more jurisdictions published: Alabama, Alaska, Arkansas, Colorado, Connecticut, Delaware, District of Columbia, Hawaii, Idaho and Indiana.
  3. : 10 more jurisdictions published: Iowa, Kansas, Louisiana, Maine, Maryland, Massachusetts, Michigan, Minnesota, Mississippi and Missouri.
  4. : Dataset first published: 9 of 51 jurisdictions published.